দুবাই সাউথে একটি লজিস্টিকস কোম্পানির অফিস ফিট-আউট: 700 m² প্রশাসনিক অফিস, যেখানে আছে অপারেশনস ডেস্কিং, ওয়্যারহাউস ফ্লোরের দিকে মুখ করা কাচঘেরা ডিসপ্যাচ কন্ট্রোল রুম ও মিটিংয়ের সুবিধা; চালু কার্যক্রমের মধ্যেই নয় সপ্তাহে তৈরি।
সংক্ষিপ্ত উত্তর
FIXORA Decor built open-plan operations desking with structured cabling, a dispatch control room with a glazed partition overlooking the warehouse floor, management offices and a meeting room. Noisy works and a DEWA disconnection were scheduled around dispatch shifts, so the warehouse kept running throughout.
মূল তথ্য
- This Dubai South logistics office fit-out delivered a 700 m² administrative office next to a working warehouse in nine weeks, completed in October 2024.
সর্বশেষ আপডেট:
This Dubai South logistics office fit-out delivered a 700 m² administrative office next to a working warehouse in nine weeks, completed in October 2024. FIXORA Decor built open-plan operations desking with structured cabling, a dispatch control room with a glazed partition overlooking the warehouse floor, management offices and a meeting room. Noisy works and a DEWA disconnection were scheduled around dispatch shifts, so the warehouse kept running throughout.
Project at a glance
| Item | Detail |
|---|---|
| Location | Dubai South, Dubai |
| Client | Logistics company with an adjoining warehouse |
| Area | 700 m² |
| Programme | 9 weeks |
| Completed | October 2024 |
| Approvals | Dubai South authority approval of fit-out drawings; Dubai Civil Defence fire system inspection and sign-off |
The brief
A logistics company with a warehouse at Dubai South asked FIXORA Decor to fit out the adjoining administrative office, covering an operations desking area, a dispatch control room overlooking the warehouse floor, management offices and meeting rooms. The office needed to function around continuous warehouse operations next door.
Offices attached to warehouses are a category of their own. They sit between two very different environments: a clean, air-conditioned office and an industrial floor with forklifts, trucks, dust and noise. The people working in them need a direct line of sight and communication with the floor, but also a calm, comfortable place to run systems, take calls and meet customers.
Scope of work
- Dubai South authority approval for the office fit-out drawings
- Glazed partition between the dispatch control room and the warehouse floor
- Open-plan operations desking with structured cabling for warehouse management systems
- Partitioned management offices and a meeting room
- Suspended ceilings, revised lighting and mechanical, electrical and plumbing upgrades
- Final Dubai Civil Defence fire system inspection and sign-off
Challenges and how they were handled
Working next to a warehouse that never stops
Because the warehouse operated continuously next door, noisy works such as chasing and ceiling installation were scheduled around dispatch shift patterns to avoid disrupting operations. On live sites like this we typically map the client's busiest periods first, then build the works programme around them: loud and dusty tasks in quieter windows, finishing trades during peaks. It takes more planning than a vacant site, but it keeps the business earning while the office is built.
Timing the electrical shutdown
A DEWA disconnection for the office's electrical upgrade was coordinated to a low-activity period agreed with the client. In a logistics operation, a power cut at the wrong moment can stop scanning, labelling and dispatch, so the timing is a business decision as much as a technical one. Having all materials and labour ready before the shutdown keeps it short. Our article on DEWA load increases and electrical approvals covers the wider process.
Building approval time into the programme
The nine-week programme also allowed for Dubai South's own authority approval timeline for the fit-out drawings before site works began. Industrial and free-zone areas each have their own approval route, so owners should confirm with the relevant authority or master developer which applies and what it currently requires, rather than assuming the process matches another district.
Designing a dispatch control room that overlooks the floor
The glazed partition between the dispatch control room and the warehouse floor is the heart of this kind of office. When planning one, owners should think about:
- Sight lines. The glass should be positioned so supervisors can see the docks, staging lanes or racking aisles that matter most, without columns or high racking blocking the view.
- Noise. Warehouses are loud. Glazing with good acoustic performance and well-sealed frames keeps the control room usable for calls.
- Dust and temperature. Warehouses are often less tightly climate-controlled than offices. A sealed partition keeps dust out of the office and stops conditioned air leaking onto the floor.
- Glare and screens. Large windows onto a brightly lit floor can cause reflections on monitors. Desk orientation and lighting levels inside the room help.
- Fire separation. Where an office meets a warehouse, the line between them may need to meet fire-separation requirements. This is coordinated with the building's fire strategy and Civil Defence; see fire-rated doors and partitions explained.
Operations desking and cabling for warehouse systems
The upgraded cabling now properly supports the operations team's management systems. In logistics offices, structured cabling is not a background detail: warehouse management systems, label printers, scanners, dispatch screens and phones all depend on it. General points we recommend owners plan for:
- A clear count of data and power points per desk, with spare points for growth.
- Tidy, labelled cable routes so future changes do not mean tracing unmarked cables.
- Coordination with whoever manages the client's IT, so the cabling suits their equipment.
- Lighting that suits screen work: even, low-glare light rather than high-bay style fittings.
- Acoustic control in the open-plan area, since operations teams spend much of the day on the phone. See acoustic design for open-plan offices.
How a fit-out beside a live warehouse is typically sequenced
Every site is different, but on projects like this the programme usually follows the same pattern.
- Survey and operations review. Walk the office and the warehouse interface with the client's operations lead, note shift times, delivery peaks and any areas that must stay accessible.
- Design freeze and approvals. Fix the layout and glazing positions, then submit drawings to the relevant authority. Site work waits for the approval.
- Hoarding and separation. Close off the work area with dust screens, agree contractor access that avoids forklift routes, and protect equipment that stays in use.
- Noisy first fix in quiet windows. Chasing, drilling, ceiling grid installation and services work go into the periods agreed with the client.
- Electrical shutdown. The DEWA disconnection and board upgrade happen in the agreed low-activity period.
- Finishes, glazing and cabling. Quieter trades continue during operational peaks.
- Testing, Civil Defence inspection and handover. Systems are tested and signed off before the operations team moves in.
Site safety on an active logistics site
A working warehouse adds risks that an empty office floor does not have: moving forklifts, reversing trucks, high racking and busy loading docks. Owners should expect their contractor to agree site rules with the warehouse team before starting, including where workers park and enter, which routes they use, when materials can be delivered without blocking docks, and who to contact if work needs to cross into the operational area. Clear separation protects both the fit-out team and the client's staff, and keeps the client's own safety procedures intact.
Indicative cost factors
We do not publish individual project costs. As a typical, indicative 2026 range that depends on scope and is confirmed only after a site survey, a mid-range Category B office fit-out in Dubai commonly costs around AED 1,600 to AED 2,600 per m², excluding furniture, fees and 5% VAT. In warehouse-attached offices, the factors below usually move the number most.
| Cost factor | Why it matters next to a warehouse |
|---|---|
| Glazing to the warehouse floor | Larger, acoustic or fire-rated glazing costs more than standard internal partitions |
| Phased or out-of-hours working | Scheduling around shifts can add labour cost and extend programmes |
| Electrical upgrade | Board upgrades and the planned shutdown need careful coordination |
| Air-conditioning changes | New rooms and partitions may need revised ductwork and controls |
| Cabling density | Operations desks often need more points than general office desks |
For more on budgeting see office fit-out cost per sq ft in Dubai and our warehouse office fit-out guide for Dubai's industrial areas.
Result
The administrative office was completed in nine weeks without disrupting ongoing warehouse operations. The dispatch control room's glazed partition gives management a clear view of the warehouse floor, and the upgraded cabling now properly supports the operations team's management systems.
Planning checklist for a warehouse office fit-out
- Map the warehouse's shift patterns and busiest dispatch periods before setting the programme.
- Confirm which authority approves fit-out drawings for your plot and build its timeline into the start date.
- Decide exactly what the control room needs to see, then position the glazing.
- Check fire-separation requirements between office and warehouse early.
- Agree a low-activity window for any DEWA disconnection.
- Define safe contractor access routes that keep workers away from forklift traffic.
- Plan cabling with the IT team for warehouse management systems, printers and scanners.
- Allow time for the Civil Defence inspection, snagging and handover. Our snagging and handover checklist helps.
Key takeaways
- Offices next to live warehouses can be fitted out without stopping operations if noisy work follows shift patterns.
- Electrical shutdowns are timed to low-activity periods agreed with the client.
- A glazed dispatch control room needs planning for sight lines, noise, dust and fire separation.
- Structured cabling for warehouse systems is a core part of the scope, not an afterthought.
Related work: a mezzanine warehouse office in Jebel Ali Free Zone and our facility maintenance contract for a DIP logistics warehouse.
Frequently asked questions
Can an office next to a working warehouse be fitted out without closing operations?
Yes. On this project noisy works were scheduled around dispatch shift patterns and the electrical shutdown was timed to a low-activity period, so warehouse operations continued throughout.
Who approves office fit-outs in Dubai South?
On this project the drawings went through Dubai South's own authority approval before site work began. Confirm the current requirements with the relevant authority for your plot.
How long does a 700 m² warehouse office fit-out take?
This one took nine weeks including allowance for the approval timeline. Live operations, approvals and long-lead glazing usually influence the programme most.
Does glass between an office and a warehouse need to be fire-rated?
It depends on the building's fire strategy and how the spaces are separated. Check with your designer and Dubai Civil Defence requirements early so the right glazing is specified.
Why does a logistics office need structured cabling?
Warehouse management systems, scanners, label printers and dispatch screens all rely on stable data connections. Planned, labelled cabling also makes future changes easier.
Planning an office beside your warehouse?
FIXORA Decor plans fit-outs around live operations and delivers them as one turnkey fit-out. WhatsApp +971501962136, call +971 50 196 2136, or request a quote to arrange a site visit.
গ্যালারি
সাধারণ জিজ্ঞাসা
Yes. On this project noisy works were scheduled around dispatch shift patterns and the electrical shutdown was timed to a low-activity period, so warehouse operations continued throughout.
On this project the drawings went through Dubai South's own authority approval before site work began. Confirm the current requirements with the relevant authority for your plot.
This one took nine weeks including allowance for the approval timeline. Live operations, approvals and long-lead glazing usually influence the programme most.
It depends on the building's fire strategy and how the spaces are separated. Check with your designer and Dubai Civil Defence requirements early so the right glazing is specified.
Warehouse management systems, scanners, label printers and dispatch screens all rely on stable data connections. Planned, labelled cabling also makes future changes easier.