বারশা হাইটসে হোটেল অ্যাপার্টমেন্ট ভবনের রিফার্বিশমেন্ট
দুবাইয়ের বারশা হাইটসে হোটেল অ্যাপার্টমেন্ট রিফার্বিশমেন্ট: ভবন খোলা রেখেই 7 মাসে তলা ধরে ধরে 180টি গেস্ট ইউনিট ও করিডর রিফ্রেশ করা হয়েছে; নতুন ফিনিশ, পানি-সাশ্রয়ী ফিটিংস ও ফায়ার-রেটেড করিডর দরজা বসেছে, আর অতিথিদের কোনো অভিযোগ নথিভুক্ত হয়নি।
সংক্ষিপ্ত উত্তর
FIXORA Decor worked floor by floor to a release schedule agreed weekly with the operator's reservations team, renewing flooring, paint, wardrobes, bathroom fittings and corridor finishes, and the works finished without a single guest complaint logged against them. A phased, live refurbishment keeps the property trading.
মূল তথ্য
- This hotel apartment refurbishment in Barsha Heights refreshed 180 guest units, corridors and the lobby over a phased seven-month programme while the building stayed open to guests.
সর্বশেষ আপডেট:
This hotel apartment refurbishment in Barsha Heights refreshed 180 guest units, corridors and the lobby over a phased seven-month programme while the building stayed open to guests. FIXORA Decor worked floor by floor to a release schedule agreed weekly with the operator's reservations team, renewing flooring, paint, wardrobes, bathroom fittings and corridor finishes, and the works finished without a single guest complaint logged against them.
This case study explains how a live hotel refurbishment is planned, what was replaced, how noise and access were managed, and the lessons operators can apply to their own properties in Dubai.
Project at a glance
| Item | Detail |
|---|---|
| Location | Barsha Heights, Dubai |
| Client | Hotel apartment operator |
| Scale | 180 guest units plus corridors and lobby |
| Duration | 7 months, phased |
| Completed | February 2025 |
| Key works | Guest unit finishes, corridor and lobby upgrade, fire-rated door sets, water-efficient bathroom fittings, minor electrical upgrades |
The brief
A hotel apartment operator in Barsha Heights needed guest units and common corridors refurbished to a current standard without closing the building to guests, since the property remained in operation throughout. Closing a hotel apartment for refurbishment is often the simplest option for a contractor but the most expensive for an owner, because every closed night is lost revenue and lost visibility on booking platforms. A phased, live refurbishment keeps the property trading.
Scope of work
- Refresh of guest unit finishes including flooring, paint, wardrobes and bathroom fixtures
- Corridor and lobby finishes upgrade with new lighting and fire-rated door sets
- Replacement of ageing shower mixers and WCs with current water-efficient fittings
- Minor electrical upgrades to guest units, including USB-equipped sockets
- Coordination with the operator's housekeeping and front-office teams on a floor-by-floor works calendar
Challenges and how they were solved
Working only between check-out and the next booking
Keeping the building operational meant FIXORA Decor could only work on units once guests had checked out and before the next booking, so the programme was built around a floor-by-floor release schedule agreed weekly with the operator's reservations team. This turns the usual contractor logic on its head: instead of the contractor deciding which rooms to work in next, the reservations team decides which rooms can be released, and the programme follows.
Keeping noise away from guests
Noisy works were scheduled away from occupied floors wherever the booking pattern allowed. Demolition of old flooring, drilling for fixtures and removal of bathroom fittings are the noisiest tasks, so they are the ones most worth timing carefully. Quieter work such as painting, wardrobe installation and fitting electrical accessories is far easier to carry out near occupied rooms.
The result
The refurbishment was completed across all floors without a single guest complaint logged against the works, and the operator reported improved guest satisfaction scores for room condition once the programme concluded.
How a live hotel apartment refurbishment is typically planned
Every property is different, but operators planning similar work should expect a sequence like this. Our guide to planning a hotel apartment refurbishment in Dubai covers each stage in more detail.
- Condition survey. Record the state of every unit type, bathroom, corridor and door so the scope is based on facts rather than assumptions.
- Mock-up unit. On projects like this we typically recommend refurbishing one unit first as a sample, so the operator can approve finishes and the contractor can time each task accurately.
- Approvals. Building management approval and any authority approvals for corridor works, especially fire-rated doors and lighting. Check the current requirements with the relevant authority and Dubai Civil Defence.
- Procurement. Order flooring, fittings, door sets and joinery in quantities that match the phasing, with storage arranged in the building.
- Phased works. Release floors or groups of units in agreed batches, refurbish, clean and hand back for housekeeping inspection before resale.
- Snagging per phase. Close out each batch before moving on, rather than leaving all snags for the end.
Floor-by-floor versus full closure
| Approach | Advantages | Drawbacks |
|---|---|---|
| Floor-by-floor, building open | Revenue continues, guests and booking visibility retained, finishes can be refined after early phases | Longer overall programme, needs tight coordination, noise and access must be managed |
| Partial closure (blocks of floors) | Faster than single floors, some revenue retained | Larger share of inventory offline at once |
| Full closure | Fastest construction, simplest logistics | No revenue during works, guests and rankings may need rebuilding |
Our article on refurbishing hotel rooms while staying open explains how to weigh these options for your property.
Material and fitting choices for hotel apartments in Dubai
- Flooring. Guest units see heavy luggage, frequent cleaning and quick turnarounds. Durable, easy-clean floors suited to air-conditioned interiors are the priority; our flooring service covers the main options.
- Paint. Washable, scuff-resistant finishes in low-odour formulations let units return to sale quickly. See our painting service.
- Wardrobes and joinery. Hinges, runners and doors take daily use from many different guests; robust hardware and moisture-resistant boards last longer in Dubai's humid coastal climate.
- Bathroom fittings. Water-efficient mixers and WCs reduce consumption across a large number of units, which adds up in a building with high occupancy.
- Electrical. USB-equipped sockets are a small upgrade that guests notice immediately, because almost everyone travels with phones and tablets to charge.
Protecting the guest experience during works
The measure of a live refurbishment is not only the finished rooms but whether guests noticed the work at all. On projects like this, these practices typically make the difference:
- Clean routes. Materials and debris move through service lifts and back-of-house corridors where the building allows, and lift interiors are protected so guests never see dusty panels.
- Contained work areas. Doors to units under refurbishment stay closed, dust protection is used at thresholds, and corridors are cleaned at the end of every shift.
- Tidy presentation. No tools, packaging or offcuts left in public areas, and site signage kept discreet.
- Clear communication. Front office staff know which floors are active each week so they can allocate rooms sensibly and answer guest questions confidently.
- Quality gate before resale. Housekeeping inspects each refurbished unit before it returns to inventory, so the first guest in the new room sees it at its best.
Barsha Heights is a dense, high-rise district with a mix of residential, office and hotel apartment towers, so access, parking for deliveries and lift availability all need planning in advance with building management.
Fire-rated corridor doors
Corridors in hotel apartment buildings are escape routes, so the doors from units and service rooms onto them play an important role in fire compartmentation. Replacing door sets in corridors means using certified fire-rated assemblies, including the frame, ironmongery, seals and closers, and installing them correctly so they perform as tested. Our explainer on fire-rated doors and partitions in UAE buildings covers what owners should check.
Cost factors for a hotel apartment refurbishment
Budgets depend on the building and are confirmed after a survey. The main drivers are:
- Number of units and the mix of unit types
- Depth of the refresh: cosmetic finishes only, or bathrooms and joinery too
- Corridor and lobby scope, including lighting and fire-rated doors
- Phasing constraints, such as small batches and restricted noisy-work windows
- Storage and logistics within the building
- Specification of flooring, fittings and joinery
VAT at 5% applies to refurbishment invoices. Small batches and restricted hours can increase the programme length, but this is usually outweighed by keeping the property open.
Planning checklist for hotel apartment operators
- Involve reservations, housekeeping and front office before the programme is set
- Approve a mock-up unit before ordering materials in bulk
- Agree a weekly release meeting and a single point of contact on each side
- Define which tasks count as noisy and when they may be carried out
- Keep a separate service lift or route for materials and debris where possible
- Protect corridors, lifts and lobby finishes during works
- Sign off each batch of units before guests are allowed back in
- Plan ongoing maintenance after the refurbishment to protect the investment
After a refurbishment, a structured maintenance contract keeps the new finishes in good condition; our hotel apartment AMC case study shows how preventive work can also be scheduled around bookings. For a similar floor-by-floor programme in a hotel, see our Downtown Dubai hotel guest room refurbishment.
Key takeaways
- A live refurbishment keeps revenue flowing, but the programme must follow the booking calendar.
- Weekly coordination with reservations is the backbone of a phased hotel project.
- Schedule noisy work away from occupied floors wherever possible.
- Fire-rated corridor door sets must be installed as complete, certified assemblies.
- Water-efficient fittings and durable finishes pay back across a large unit count.
Frequently asked questions
Can a hotel apartment be refurbished without closing?
Yes. This Barsha Heights building stayed open throughout a seven-month programme, with units released floor by floor between guest stays.
How long does a hotel apartment refurbishment take?
It depends on the number of units, the depth of the refresh and the phasing. This 180-unit project took seven months working around live bookings.
How do you keep noise down for guests during works?
Noisy tasks are scheduled away from occupied floors wherever the booking pattern allows, and quieter tasks are done near occupied rooms.
Do corridor doors need to be fire-rated?
Doors onto escape corridors usually form part of the building's fire compartmentation and need certified fire-rated door sets. Check the specific requirements with the building and Dubai Civil Defence.
What should a hotel apartment refurbishment include?
Commonly flooring, paint, wardrobes, bathroom fittings and small electrical upgrades in units, plus corridor and lobby finishes and lighting. A condition survey defines the right scope.
Planning to refurbish your hotel apartments?
FIXORA Decor can survey your building, propose a phasing plan that works with your bookings and deliver the works floor by floor. Message us on WhatsApp at +971501962136, call +971 50 196 2136, or request a quote.
গ্যালারি
সাধারণ জিজ্ঞাসা
Yes. This Barsha Heights building stayed open throughout a seven-month programme, with units released floor by floor between guest stays.
It depends on the number of units, the depth of the refresh and the phasing. This 180-unit project took seven months working around live bookings.
Noisy tasks are scheduled away from occupied floors wherever the booking pattern allows, and quieter tasks are done near occupied rooms.
Doors onto escape corridors usually form part of the building's fire compartmentation and need certified fire-rated door sets. Check the specific requirements with the building and Dubai Civil Defence.
Commonly flooring, paint, wardrobes, bathroom fittings and small electrical upgrades in units, plus corridor and lobby finishes and lighting. A condition survey defines the right scope.
সূত্র