夏季优惠:空调深度清洗立减 20% — 请于六月 30 日前预约立即预约
跳至内容

阿布扎比 Khalifa City 别墅会客厅新建

阿布扎比 Khalifa City 一栋别墅花园中新建的 64 m² 独立会客厅 (Majlis),含客用卫生间和备餐间,由 FIXORA Decor 在十八周内建成,涵盖许可、结构、机电、木工和传统细节。

快速解答

阿布扎比 Khalifa City 一栋别墅花园中新建的 64 m² 独立会客厅 (Majlis),含客用卫生间和备餐间,由 FIXORA Decor 在十八周内建成,涵盖许可、结构、机电、木工和传统细节。 This majlis build in Abu Dhabi created a 64 m² standalone majlis, guest washroom and small serving pantry in the front garden of a Khalifa City villa in eighteen weeks.

关键信息

  • Washroom waterproofing flood tested for 24 hours

最后更新:

This majlis build in Abu Dhabi created a 64 m² standalone majlis, guest washroom and small serving pantry in the front garden of a Khalifa City villa in eighteen weeks. The family wanted a proper place to receive guests during Ramadan, Eid and weekly gatherings without bringing visitors through the main house. FIXORA Decor handled design coordination, permits, construction and interiors. This illustrative case study describes a typical majlis project of this kind, from the brief to aftercare.

Majlis build in Abu Dhabi: the brief

The owner's family regularly hosted twenty to thirty men on Thursday evenings and many more during Ramadan and Eid. The existing formal living room inside the villa was being used as a majlis, which meant guests passed the family areas, the women of the household were confined upstairs during gatherings, and the room was too small. A tent in the garden had been used for larger occasions, but it was hot, noisy and needed to be rented each time.

The family asked for:

  • A separate building with its own entrance from the street-side gate, so guests never enter the main house
  • Seating for around thirty people on traditional floor-level cushions along the walls, with space for low tables
  • A guest washroom with ablution area and a small pantry for serving qahwa, dates and food brought from the main kitchen
  • Strong, quiet air-conditioning able to cope with a full room on an August evening
  • A design that felt Emirati and generous, but not heavy or dark
  • Completion before Ramadan, which set a firm end date

Challenges

A fixed deadline

The family's real deadline was the first night of Ramadan. Working back from that date, the programme left little float for approvals, so drawings had to be right the first time and long-lead items such as the AC units, windows and carved timber door had to be ordered as soon as the design was frozen.

Plot rules and setbacks

Khalifa City plots have rules on building lines, setbacks from boundaries and maximum coverage. The first location the owner preferred, tight against the front boundary wall, was outside the permitted line. The majlis was moved slightly back and rotated so that its entrance still faced the guest gate, and a shaded walkway linked the two.

Heat load with a full room

Thirty people, lights, a coffee station and a west-facing elevation create a large cooling load. Undersized AC is the most common complaint we hear about existing majlis rooms, so cooling was designed for peak occupancy, not for an empty room.

Acoustics

Hard floors, plaster walls and a high ceiling make a majlis echo, which tires guests and makes conversation difficult. Acoustic treatment had to be built in without making the room look like an office.

Approvals obtained

A new standalone building on a villa plot needs a building permit in Abu Dhabi, just as an extension does. The process below is the general route we followed; owners should confirm the current steps, documents and fees with the municipality and their consultant before starting.

  • Design by a licensed consultant: architectural, structural and MEP drawings prepared and stamped by a consultant registered with the municipality
  • Building permit: submitted through the municipality's online system, with plot plan, ownership documents and drawings
  • Civil defence requirements: fire detection, extinguisher and exit provisions included in the drawings
  • Utility connection: load assessment and connection approval from the electricity distribution company for the new board and AC units
  • Inspections and completion: stage inspections during construction and a completion certificate at the end

Approvals took around six weeks. Design development, joinery shop drawings and material sampling ran in parallel, so the site team was ready to mobilise the day the permit was issued.

Design approach

The design took cues from traditional Emirati architecture without copying it. The outside is a simple, light-coloured rendered volume with a parapet, slim vertical windows and a deep shaded entrance. Inside, the room is generous and calm.

  • Proportion: a 4.2 m ceiling with a central coffered panel gives the room height and air, and lowers to 3.0 m around the perimeter where the AC and lighting are hidden
  • Light: high clerestory windows on the north side bring daylight without glare or overlooking, while the west wall has no glazing at all
  • Materials: a pale stone-look porcelain floor, warm timber wall panels at seated height and textured plaster above
  • Detail: geometric mashrabiya-style timber screens on the entrance and coffee station, made in CNC-cut MDF and lacquered for durability
  • Flexibility: floor seating along the walls, with sockets at low level for phone charging and a concealed television behind sliding screens for matches and news
  • Separation: the pantry has a hatch to the majlis and a separate door to a covered path back to the main kitchen, so food can be served without staff crossing the guest area

Scope of work

  • Site survey, setting out and liaison with the licensed consultant
  • Excavation, footings, ground beams and termite treatment
  • Reinforced concrete columns, beams and roof slab
  • Insulated blockwork walls, cement render and external elastomeric paint
  • Roof waterproofing, insulation and protection tiles
  • Thermally broken aluminium windows and a carved solid timber entrance door
  • Electrical sub-board, lighting, sockets, data and television points, fire alarm devices
  • Ducted air-conditioning sized for full occupancy, with quiet linear diffusers
  • Water supply and drainage to the washroom, ablution area and pantry
  • Gypsum ceilings with a coffered central feature and concealed LED lighting
  • Porcelain flooring and skirting throughout
  • Timber wall panelling with integrated acoustic panels
  • Pantry joinery with sink, under-counter fridge and space for coffee equipment
  • Washroom tiling, sanitaryware and ablution taps
  • Covered walkway from the guest gate and landscaping repairs around the building

Materials and finishes

AreaFinishReason
Majlis floorLarge-format stone-look porcelain, mattCool underfoot, hard-wearing and easy to clean after events
Lower wallsTimber veneer panels with perforated acoustic sectionsWarmth at seated height and reduced echo
Upper wallsTextured mineral plaster in warm whiteTraditional character, hides minor marks
CeilingGypsum board with coffered centre and cove lightingHeight and soft indirect light
ScreensCNC-cut MDF, lacquered, geometric patternTraditional feel with modern durability
WashroomSlip-resistant floor tile, full-height wall tile, ablution taps and drainagePractical for frequent use
PantryQuartz worktop, moisture-resistant cabinetsResists coffee, cardamom and saffron stains
Entrance doorSolid hardwood, carved panels, oil finishA strong first impression for guests

Programme and phasing

WeeksStageMain activities
1–6Design and permitSurvey, design, consultant drawings, permit, ordering long-lead items
7–9SubstructureExcavation, footings, ground beams, backfill
10–12SuperstructureColumns, roof slab, blockwork, roof waterproofing
13–14Envelope and first fixWindows, render, electrical, plumbing and AC first fix
15–17InteriorsCeilings, flooring, panelling, screens, washroom, pantry
18CommissioningAC balancing, testing, cleaning, snagging, completion inspection

Because the majlis was a separate building, the family's daily life was barely affected. Deliveries came through the guest gate, the garden was hoarded off, and work stopped for prayer times and at sensible hours in the evening.

Quality and safety

  • Concrete cubes taken and tested for every structural pour
  • Roof flood test before insulation and tiling
  • Washroom waterproofing flood tested for 24 hours
  • AC commissioning with a full-load check, measuring supply air and room temperature with all units running
  • Electrical insulation and earth tests before energising, with labelled circuits
  • Safe access to the roof with guard rails during slab and waterproofing work
  • Heat stress management during warmer months, with early starts, shade and water on site
  • Hoarding to keep the family's children away from excavations and machinery

Handover and aftercare

The majlis was handed over two weeks before Ramadan, which gave the family time to bring in cushions, rugs and coffee equipment. The handover pack included as-built drawings, permit and completion documents, test certificates, warranties for AC, windows and waterproofing, and care instructions for the timber door and panels.

FIXORA Decor visited during the second week of Ramadan to check the AC under real load. One diffuser was adjusted to stop a draught falling on the main seating corner. At six months the timber door was re-oiled and the external paint checked for sand abrasion. The owner now has the majlis on an annual maintenance plan with AC servicing before each summer.

Results

  • A dedicated majlis seating around thirty guests comfortably
  • Guests arrive and leave without entering the family home
  • The room stays cool on full evenings and conversation is easy thanks to acoustic treatment
  • Tent hire for Ramadan and Eid is no longer needed
  • Building fully permitted and recorded, adding value to the property

Standalone majlis buildings of this size typically fall in an indicative 2026 range of roughly AED 4,000 to AED 7,500 per square metre in Abu Dhabi or Dubai, depending on structure, ceiling height, carpentry and AC specification, plus design and authority fees and 5% VAT. These are planning figures only; a site visit is needed for a real estimate.

Lessons for other owners

  • Design the AC for a full room. A majlis is judged on its worst evening, not its average one.
  • Plan the route for food and guests. Separate guest and service access makes hosting far easier.
  • Avoid west glazing. High north light gives a bright room without heat or overlooking.
  • Treat acoustics early. Panels built into joinery look intentional; panels added later look like an afterthought.
  • Work back from your occasion. If Ramadan or a wedding is the deadline, start approvals at least six months ahead.
  • Keep the permit trail. A permitted majlis adds value; an unpermitted one can be a problem at sale.

Key takeaways

  • A standalone majlis is a building project needing a permit, not an interior job.
  • Around four to five months from design to handover is realistic.
  • Cooling, acoustics and separate access matter more than decoration.
  • Traditional details can be made durable with modern materials.

Planning a majlis at home?

Whether you want a new majlis building, a garden majlis or a converted room, FIXORA Decor can advise on layout, approvals and budget for villas across Abu Dhabi, Dubai and Sharjah. Message us on WhatsApp at +971501962136, call +971 50 196 2136 or request a quote.

图库

资料来源

开启您的项目

我们的团队随时为您服务——今天就获取免费报价。

或致电我们+971 50 196 2136

服务区域