In this article
Quick answer
The office fit-out process in Dubai from start to finish: writing the brief, test-fits, landlord and authority approvals, construction, commissioning and handover. On a typical 300 to 1,000 m² office, the whole process takes roughly three to five months, of which approvals often account for four to eight weeks.
Key facts
- On a typical 300 to 1,000 m² office, the whole process takes roughly three to five months, of which approvals often account for four to eight weeks.
- Furniture and IT together frequently add 30–50% to the fit-out figure, so leaving them out of the early budget creates difficult decisions later.
- The table below shows typical cost bands for a Category B office fit-out in Dubai, exclusive of 5% VAT, furniture and IT equipment.
Last updated:
An office fit-out in Dubai moves through six stages: a written brief, a test-fit to prove the space works, detailed design, approvals from the landlord and the relevant authorities, construction, and handover with the completion certificates you need to occupy. On a typical 300 to 1,000 m² office, the whole process takes roughly three to five months, of which approvals often account for four to eight weeks. The business owners who move in on time are the ones who start the approval track early and freeze the design before construction begins.
Stage 1: Write a brief that a designer can use
A useful brief is short and specific. It should cover headcount today and in three years, the ratio of fixed desks to shared or hot desks, the number and size of meeting rooms, special rooms such as server rooms, labs, prayer rooms, wellness rooms or storage, and how visitors arrive and are received. Add your budget, the target move-in date and the lease dates, including any rent-free fit-out period offered by the landlord.
Also note what the landlord delivers. Many Dubai offices are handed over as shell and core or Category A, meaning raised floors or screed, ceiling grid, base lighting, AC to a standard layout and fire systems to an open-plan arrangement. Your fit-out, often called Category B, adapts those systems to your layout. Understanding the starting point avoids paying twice for items the landlord already provides.
Budget for more than construction
The fit-out contract is usually the largest cost, but it is not the only one. A realistic office budget also covers loose furniture and task seating, IT network equipment and cabling, audio-visual systems for meeting rooms, access control and CCTV, signage, consultant and authority fees, moving costs and a contingency of around 10%. Furniture and IT together frequently add 30–50% to the fit-out figure, so leaving them out of the early budget creates difficult decisions later.
Read the lease before the design starts
Several lease clauses shape the fit-out directly. The rent-free or fit-out period sets the deadline. The landlord's fit-out guide may specify approved contractors for fire alarm and sprinkler modifications, required ceiling and lighting standards, and the landlord's own review fees and deposit. Some buildings charge separately for AC supplied outside core hours, which matters if your team works late or at weekends. Most importantly, the reinstatement clause states whether you must return the space to its original condition when you leave. If it does, design choices such as fixed glass partitions, heavy joinery and raised platforms will carry a removal cost at the end of the lease as well as an installation cost now. Ask the landlord to confirm in writing which elements may stay.
Stage 2: Test-fit and space planning
A test-fit is a quick layout showing that your brief fits the space, ideally before you sign the lease. It checks desk numbers, meeting room counts, circulation, escape routes and travel distances, natural light, column positions and where the existing AC and sprinkler layouts will need to move. A good test-fit can show that a smaller unit works, or that a cheaper unit will cost more to fit out because of awkward geometry.
It is worth test-fitting two or three shortlisted units side by side. Compare not only desk numbers but also the cost of moving AC and sprinklers, the condition of the existing ceiling and floor, the location of risers for power and data, and whether the pantry can connect to existing drainage. These factors can shift the fit-out cost by a meaningful amount and are far easier to negotiate with the landlord before the lease is signed than after.
Stage 3: Detailed design and specification
Once the layout is agreed, the designer produces general arrangement plans, reflected ceiling plans, partition and door schedules, joinery details, a finishes schedule, furniture layouts and MEP drawings for lighting, power, data, AC, fire alarm and sprinklers. Acoustic performance of meeting rooms and the IT infrastructure should be resolved at this stage, not on site. The outcome is a tender package that contractors can price on a like-for-like basis.
Stage 4: Landlord and authority approvals
Approvals in Dubai depend on where the office sits. The landlord or building management approves first, usually against their fit-out guidelines. The authority approval then follows the free zone or jurisdiction:
- Dubai Municipality for most mainland buildings, with Dubai Civil Defence approval for fire alarm, sprinkler and life-safety changes.
- Dubai Development Authority for offices in Dubai Media City, Dubai Internet City, Dubai Production City and other DDA-managed zones.
- Trakhees for areas such as JAFZA and parts of Jebel Ali.
- Dubai Silicon Oasis Authority for offices in Dubai Silicon Oasis.
- DIFC and some other zones run their own fit-out approval processes.
DEWA is involved where the electrical load changes. Submissions are made by a registered consultant or approved contractor, and fees apply. Once works finish, inspections lead to a completion or fit-out certificate, and Civil Defence sign-off is usually required before the business can obtain or renew certain licenses. Plan the program around these steps rather than around the construction alone.
Stage 5: Construction
Commercial fit-out construction follows a familiar order: site setup and protection, partitions and framing, above-ceiling MEP works, AC and sprinkler modifications, ceilings, flooring, joinery, glazing, decoration, then furniture and IT installation. Most office buildings restrict noisy work to evenings, nights or weekends when neighboring tenants are occupied, which affects both the program and the labor cost. Long-lead items such as glass partitions, acoustic doors, bespoke joinery and imported carpet tiles should be ordered as soon as the design is frozen.
The table below shows typical cost bands for a Category B office fit-out in Dubai, exclusive of 5% VAT, furniture and IT equipment. They are indicative ranges only.
| Specification | Typical features | Typical range (AED per m²) | Typical site duration (500 m²) |
|---|---|---|---|
| Basic | Open plan, a few meeting rooms, standard ceilings and carpet tiles | 350–700 | 6–8 weeks |
| Mid-range | Glass meeting rooms, feature reception, pantry, acoustic treatment | 700–1,300 | 8–12 weeks |
| Premium | Bespoke joinery, high-end finishes, extensive glazing, upgraded AC zoning | 1,300–2,200 | 12–16 weeks |
FIXORA Decor runs commercial sites with a weekly program review so that out-of-hours work, deliveries and inspections are booked in advance rather than discovered late. Our article on fit-out timelines and what causes delays explains where the weeks usually go.
Stage 6: Testing, commissioning and handover
Before occupation, systems must be tested and commissioned: AC balancing, fire alarm cause-and-effect testing, emergency lighting, sprinkler pressure tests, power and data testing and access control. Snagging lists are prepared and closed. The handover pack should include as-built drawings, test certificates, warranties, operation and maintenance manuals and the authority completion certificates. Keep these together, because they are needed for future modifications, lease renewals and, eventually, the reinstatement at the end of the lease.
Common mistakes
- Signing a lease without a test-fit, then discovering the space cannot hold the required headcount.
- Changing the layout after approval drawings are submitted, which restarts parts of the approval process.
- Ignoring reinstatement obligations in the lease, which can cost as much as a basic fit-out when you leave.
- Leaving IT, security and AV contractors out of design coordination until the ceilings are closed.
- Underestimating out-of-hours working requirements in occupied buildings.
Next step
If you are moving or expanding, send us the floor plan, your headcount and target move-in date, and FIXORA Decor will prepare a test-fit and a free quotation. Our turnkey fit-out service covers design, approvals, construction and handover under a single contract.
The information in this article is general guidance, not advice for your specific project. See our Terms.
Frequently asked questions
Sources
Was this article helpful?
Get new articles by email
Practical tips now and then. Confirm by email, unsubscribe any time.