Quick answer
What reinstatement and dilapidation works mean when leaving an office in Dubai: lease obligations, typical scope, costs per m², timelines and how to pass the landlord inspection. Reinstatement works return a leased office to the condition required by the lease when you leave, and dilapidations are the landlord's claim for any repairs or reinstatement you did not complete.
Key facts
- 3–6 months before exit: review lease obligations, request the landlord's reinstatement requirements, commission a survey and cost estimate.
- 2–3 months before: agree scope with the landlord in writing, including any items they accept to keep.
- 1–2 months before: obtain building management approvals and permits, book lifts and waste removal.
Last updated:
Reinstatement works return a leased office to the condition required by the lease when you leave, and dilapidations are the landlord's claim for any repairs or reinstatement you did not complete. In most Dubai commercial leases, the tenant must remove its fit-out and hand back the space in shell and core, Category A or handover condition, in good repair, before the lease expires. Typical reinstatement costs range from AED 100 to AED 400 per m² depending on the scope, and the works usually take two to six weeks for a 200–1,000 m² office.
Understand your lease obligations
Start with the lease. The relevant clauses are often found under yield-up, reinstatement, alterations or handback. Look for:
- Handback condition: shell and core, Category A (with ceilings, lighting and AC distribution), or the condition at handover as recorded in a schedule or photographs.
- Timing: whether reinstatement must be complete before the lease end date, and whether you are charged rent for extra time.
- Landlord's option: some leases allow the landlord to accept certain fit-out items, such as glass partitions or a pantry, instead of removal. Ask early, because an incoming tenant may want them.
- Approvals: reinstatement works normally need building management approval and sometimes authority permits.
- Deposit: the security deposit is usually released only after the landlord accepts the space.
If the handover condition was not documented when you moved in, ask the landlord for their records or the building's Category A specification. Disagreements over the original condition are a common source of dispute.
Typical reinstatement scope
Every office is different, but a typical scope includes:
- Removal of partitions, glazed offices, doors and built-in joinery.
- Removal of tenant ceilings, bulkheads and decorative features, and reinstatement of the base building ceiling grid if required.
- Removal of carpet, raised floor additions or tenant flooring, and making good the screed or base floor.
- Disconnection and removal of tenant electrical, data and audio-visual cabling back to source, leaving safe, capped and labeled circuits.
- Reinstatement of AC distribution, diffusers and fan coil units to base building layout, and rebalancing.
- Reinstatement of fire alarm, sprinkler and emergency lighting to base building layout, with Dubai Civil Defence or building fire contractor sign-off where required.
- Removal of pantry and plumbing, capping pipes at approved points.
- Repairs to walls, columns and façade glazing, repainting to base building color.
- Removal of signage and making good.
- Final cleaning and waste disposal through approved channels.
Typical costs
| Handback condition | Typical range | Comments |
|---|---|---|
| Make good only (painting, repairs, cleaning) | AED 40–100 per m² | Where the landlord accepts the fit-out |
| Back to Category A | AED 100–250 per m² | Remove partitions and finishes, reinstate ceilings and services layout |
| Back to shell and core | AED 150–400 per m² | Full strip-out including ceilings, raised floor and MEP distribution |
Ranges are typical, exclusive of 5% VAT. Fire system modifications by building-nominated contractors, authority fees and waste disposal can add significantly, so obtain those quotations early. Salvage value of glass partitions or furniture rarely offsets much of the cost, but reuse in your new office can help.
Timeline and program
Most tenants run reinstatement in the final weeks of the lease, after moving out. A practical sequence:
- 3–6 months before exit: review lease obligations, request the landlord's reinstatement requirements, commission a survey and cost estimate.
- 2–3 months before: agree scope with the landlord in writing, including any items they accept to keep. Appoint the contractor.
- 1–2 months before: obtain building management approvals and permits, book lifts and waste removal.
- After move-out: strip-out, MEP reinstatement, making good, fire system testing, cleaning.
- Final week: joint inspection, snag closure, key handover and final DEWA reading.
If you are moving to new premises, coordinate this with your wider plan; our office relocation checklist for Dubai covers the full timeline.
Passing the landlord inspection
The handover inspection is where deposits are won or lost. Prepare by:
- Inviting the landlord's representative to a pre-inspection a week before the end, so snags can be closed in time.
- Providing test certificates for fire alarm, sprinklers and electrical installation, plus as-built drawings if required.
- Taking dated photographs and video of every area at completion.
- Agreeing the final condition in writing, signed by both parties.
- Returning access cards, keys and parking permits.
Managing cost and building rules
Towers, free zones and building management
Reinstatement in a managed tower or free zone follows the building's own rules. Building management usually requires a work permit, insurance certificates, method statements and a deposit before works can start. Noisy strip-out may be limited to evenings and weekends in occupied buildings, which extends the program and raises labor costs. Fire alarm and sprinkler modifications are often restricted to the building's nominated contractor, and the final system test must be witnessed. In free zones, the zone authority may require its own permit and completion inspection. Check these rules early, because they affect both price and timing.
Ways to reduce reinstatement cost
- Ask the landlord what can stay. Partitions, ceilings, flooring and pantries in good condition may be welcome to the next tenant.
- Talk to the incoming tenant. If a new tenant is lined up, they may take over parts of your fit-out, with the landlord's agreement.
- Reuse items in your new office. Glass partitions, joinery, furniture and AV equipment can sometimes be relocated.
- Combine contracts. Using one contractor for both the new fit-out and the old office reinstatement simplifies logistics and can lower overall cost.
- Plan early. Last-minute works cost more because of rushed scheduling, premium labor rates and extra rent if you overrun.
Waste and recycling
Strip-out generates significant waste. Approved waste contractors must remove debris, and metals, glass, carpet tiles and timber can often be separated for recycling. Ask for waste transfer records, which some landlords and corporate sustainability teams request.
Negotiating dilapidations
If you do not complete reinstatement, the landlord may carry out the works and claim the cost, often with fees added. Claims should reflect reasonable costs for the obligations actually in the lease. If you receive a dilapidations schedule, check each item against the lease, challenge items that represent improvements beyond the original condition, and ask for supporting quotations. Professional advice is worthwhile for larger claims.
Budgeting for exit early
Reinstatement is easy to forget when a business is focused on finding and fitting out a new office. Build the cost into the relocation budget from the start, and if the lease still has several years to run, consider keeping a provision in the accounts. When negotiating a new lease, try to agree the handback condition clearly and record the condition at handover with photographs and a signed schedule. That single step can save considerable time and money when you eventually leave.
What to watch out for
- Leaving the lease review until the final month.
- Assuming the landlord wants everything removed without asking.
- Forgetting the cost of nominated fire system contractors.
- Overrunning the lease end and paying extra rent or penalties.
- No signed record of the final condition.
FIXORA Decor carries out reinstatement surveys, prices the scope against the lease and manages the works through to landlord sign-off. Where we also deliver your new office, FIXORA Decor aligns both programs so you are not paying for two sites longer than necessary.
Next step
Send us your lease clause, floor plan and exit date, and we will provide a scope and estimate. Request a free quotation or see our turnkey fit-out service for strip-out and reinstatement.
The information in this article is general guidance, not advice for your specific project. See our Terms.