Classroom and science lab refresh at a private school in Muwaileh, Sharjah
An illustrative school classroom refurbishment in Muwaileh, Sharjah: 18 classrooms, two science labs and a learning commons refreshed in the summer break, with acoustic ceilings, better lighting, durable flooring and flexible furniture.
Quick answer
An illustrative school classroom refurbishment in Muwaileh, Sharjah: 18 classrooms, two science labs and a learning commons refreshed in the summer break, with acoustic ceilings, better lighting, durable flooring and flexible furniture. This case study is an illustrative example; the school is not named.
Key facts
- Eight weeks for 21 rooms meant several trades working in parallel and no room for late material deliveries.
Last updated:
This school classroom refurbishment in Sharjah refreshed 18 classrooms, two science laboratories and a shared learning commons at a private primary and middle school in Muwaileh during the eight-week summer break. FIXORA Decor replaced ceilings, lighting, flooring and storage, upgraded the labs, improved acoustics and installed flexible furniture, then handed every room back clean and ready for the teachers' return. This case study is an illustrative example; the school is not named.
The brief: a school classroom refurbishment finished before term
The school had grown quickly and its classrooms were showing their age. Ceiling tiles were stained from old AC leaks, fluorescent lights flickered, vinyl flooring was lifting at joints, and noise from corridors and neighboring rooms made group work difficult. Teachers also wanted more flexible rooms: furniture that could move from rows to groups in minutes, more wall space for display and writing, and storage that kept resources off the floor.
The two science labs were the second priority. Their worktops were damaged, sinks drained slowly, and gas taps on the student benches were no longer used and needed to be safely removed. The leadership team wanted labs that suited practical work for younger students, with better ventilation, chemical-resistant surfaces and a teacher demonstration bench visible from every seat.
The one fixed condition was time. All work had to be finished, cleaned and inspected before teachers returned for their preparation week at the end of August, with no exceptions.
Challenges
- Fixed deadline. Eight weeks for 21 rooms meant several trades working in parallel and no room for late material deliveries.
- Summer heat. July and August temperatures in Sharjah are extreme. The building's central AC was partly shut down for maintenance by another contractor, so we needed temporary cooling for some zones.
- Child safety. Every detail had to suit children: rounded edges, no exposed sockets at low level, toughened glass, slip-resistant floors and stable furniture.
- Hidden AC problems. Stained ceiling tiles pointed to leaking condensate drains and poorly insulated chilled water pipes above the ceiling, which needed fixing before new ceilings went in.
- Coordination with other summer works. The school had separate contractors for AC servicing, IT and painting of external areas, all on site at the same time.
Approvals (in general terms)
School works in Sharjah generally involve the school owner and operator, the building's landlord if the premises are leased, and the relevant municipal and Civil Defence approvals for fit-out works that affect ceilings, fire detection, lighting, exits or electrical loads. Private schools also need to keep in line with the education regulator's requirements for learning spaces, so the school's leadership confirmed that the new layouts and lab arrangements met their expectations. Gas removal in the labs was handled by a qualified gas contractor with proper capping and testing. We provided drawings, product fire ratings and method statements for the submissions; current fees and processes should always be confirmed directly with each authority.
Design approach
We designed one standard classroom layout and tested it with a group of teachers using a full mock-up in the first week. The final design uses:
- Acoustic ceilings with high sound absorption tiles to reduce echo, so teachers do not have to raise their voices and group work is calmer.
- LED panel lighting with good glare control, a separate dimmable row near the board for projector use, and daylight-linked control at window rows.
- Heterogeneous vinyl flooring with welded seams, chosen for durability, easy cleaning and comfort underfoot.
- A teaching wall with a whiteboard, interactive screen bracket, pin-up fabric panels on either side and lockable cupboards below.
- Perimeter storage under the windows with labeled trays for resources, at heights suitable for each age group.
- Mobile furniture: trapezoid tables that form groups of four, six or eight, stackable chairs in sizes matched to each grade, and two soft seating cubes for a reading corner.
In the science labs, we replaced the fixed rows of benches with perimeter benches with sinks and four central island tables, so students face the teacher during explanations and turn to the benches for practical work. Worktops are solid-grade phenolic resin, which resists chemicals, heat and scratches. A fume cupboard was relocated near an external wall for better ducting, an eyewash station and emergency shower were added, and lockable chemical storage was ventilated to outside.
The learning commons, an underused corridor widening, became a reading and project space with acoustic wall panels, carpet tiles, low bookcases and a writable wall.
Scope of work
- Removal of old ceilings, lights, flooring, boards and fixed furniture
- Repair of condensate drains and re-insulation of chilled water pipes above ceilings with the AC contractor
- Acoustic suspended ceilings and re-positioning of smoke detectors and speakers with the fire alarm contractor
- LED lighting, controls and new sockets above child height, with additional data points for the IT contractor
- Floor leveling and welded-seam vinyl flooring with coved skirting in labs
- Teaching walls, storage joinery and pin-up panels
- Science lab benches, phenolic worktops, sinks, eyewash and emergency shower, fume cupboard relocation, gas capping and testing
- Learning commons finishes and furniture
- Painting of classroom walls in washable paint
- Supply and installation of loose furniture
Materials
| Element | Material | Why it suits a school |
|---|---|---|
| Ceiling | Mineral fiber acoustic tiles, high absorption class | Reduces noise and echo, tiles easy to replace |
| Classroom floor | Heterogeneous vinyl, welded seams | Hard-wearing, hygienic, comfortable |
| Lab worktops | Solid phenolic resin | Chemical, heat and scratch resistance |
| Walls | Washable matte emulsion, low VOC | Cleans easily, minimal odor for children |
| Display walls | Fabric-faced pin-up panels | Display space that also absorbs sound |
| Storage | HPL-faced moisture-resistant board, rounded edges | Durable and child-safe |
| Lighting | LED panels with low glare, 4000K | Good visibility for reading, lower energy use |
Program: eight weeks of summer works
Long-lead items, especially lab worktops, the fume cupboard and furniture, were ordered in May so they arrived before the break. The program then ran zone by zone:
- Week 1: mock-up classroom, strip-out of the first block, protection of corridors and stairs.
- Weeks 2–3: AC drain and pipe insulation repairs, electrical first fix, gas capping in labs, strip-out of the second block.
- Weeks 4–5: ceilings, lighting and floor leveling in block one; lab benches and services installation.
- Week 6: flooring, teaching walls and storage in block one; ceilings and lighting in block two.
- Week 7: flooring and joinery in block two, learning commons, lab commissioning.
- Week 8: furniture installation, snagging, deep cleaning, inspections and handover room by room.
Heavy and noisy work was arranged early in the day while it was cooler, temporary spot coolers were used in zones without central AC, and the team followed midday break rules for any outdoor tasks such as unloading deliveries.
Handover
Each room was handed over with a checklist signed by the school's facilities manager. The final handover pack included as-built drawings, electrical and gas test records, fume cupboard commissioning results, product data sheets and warranties, a furniture inventory per room and a cleaning guide for the vinyl, phenolic worktops and fabric panels. Spare ceiling tiles and flooring were left in the maintenance store. A 12-month defects period applies, and we carried out a check visit in the first half-term to deal with any small issues once the rooms were in daily use.
Safety on an empty school site
Even with no students present, a school in summer is not an empty building: administrators, admissions staff and other contractors were on site most days. We fenced off each work zone, kept corridors and exits clear, and agreed a single delivery route away from the admissions entrance where families visited. All our staff completed the school's safeguarding induction, wore identification at all times and signed in and out at security.
Results
- All 18 classrooms, two labs and the learning commons were ready for the teachers' preparation week.
- Teachers report quieter, calmer rooms and less need to raise their voices.
- Furniture can move from rows to groups in a few minutes, supporting collaborative lessons.
- Labs are safer, with unused gas removed, eyewash and emergency shower installed and better ventilation.
- No new ceiling stains since the AC drains and pipe insulation were repaired.
Lessons learned
The summer break is shorter than it looks once delivery times, inspections and cleaning are counted, so ordering long-lead items before the break is essential. Fixing the AC problems above the ceilings was the most important hidden task: replacing stained tiles without fixing the cause would have brought the stains back within months. Testing a mock-up classroom with teachers in week one led to several practical changes, including lower storage heights for younger grades and more sockets at the teacher's desk. Finally, a single weekly coordination meeting with all summer contractors avoided clashes over ceilings, cabling and access.
Key takeaways
- Order lab worktops, furniture and fume cupboards before the summer break.
- Fix AC leaks and pipe insulation before installing new ceilings.
- Use acoustic ceilings and pin-up panels to make classrooms quieter.
- Test a mock-up classroom with teachers before rolling out.
Planning a school or nursery refurbishment?
Indicative 2026 budgets for a classroom refresh of this kind typically range from around AED 35,000 to AED 75,000 per classroom plus 5% VAT, with science labs costing more depending on services and equipment; we confirm prices after a survey. Contact FIXORA Decor on WhatsApp +971501962136 or call +971 50 196 2136 to plan your next summer program, or request a quote at /quote.