DIFC Law Firm Office Expansion and Live Refurbishment

A DIFC law firm took an adjoining unit and refurbished its existing office while staying open: new partner offices, a hearing-ready boardroom, secure file storage and a reception upgrade, phased over 12 weeks of mostly after-hours work.

Quick answer

A DIFC law firm took an adjoining unit and refurbished its existing office while staying open: new partner offices, a hearing-ready boardroom, secure file storage and a reception upgrade, phased over 12 weeks of mostly after-hours work. Law firm office refurbishment in DIFC: FIXORA Decor expanded and refurbished the office of a DIFC law firm while the lawyers kept working.

Key facts

  • A disputes and corporate law firm had grown from 30 to almost 45 people in three years.

Last updated:

Law firm office refurbishment in DIFC: FIXORA Decor expanded and refurbished the office of a DIFC law firm while the lawyers kept working. We fitted out an adjoining unit of about 320 m², joined it to the firm's existing 540 m² office, and refurbished the original space in four phases, with most noisy work done at night and on weekends, over 12 weeks.

This is an illustrative case study of a live office refurbishment in DIFC. It shows how we handled confidentiality, phasing, approvals and acoustic privacy for a professional services client. The firm is not named.

The brief

A disputes and corporate law firm had grown from 30 to almost 45 people in three years. When the unit next door in the same DIFC building became available, the managing partner took it and asked us to create one connected office. The brief had three parts:

  • Expansion: fit out the new unit with six partner offices, an associate pod for 12, a secure file room and a second, smaller meeting room.
  • Refurbishment: update the existing office, which was nearly ten years old, with a new reception, a larger boardroom suitable for mediation sessions and witness preparation, new carpets, lighting and paint throughout.
  • Continuity: the firm could not close. Client meetings, hearings by video link and filing deadlines continued throughout the works.

Confidentiality was the firm's first concern. Contractor staff could not see documents or screens, and no work could take place in an occupied office during the working day.

Challenges

Working around live legal work

Lawyers work late, especially before hearings. A standard "works after 6 pm" approach would not have been enough. We agreed a daily handover with the office manager: rooms released to us each evening were listed by 5 pm, and anything not on the list stayed untouched.

Joining two units

The new unit and the existing office shared a partition wall and a corridor. Creating one connected office meant removing part of that wall, re-routing services across the line, and making sure the fire compartment and escape routes still worked under the building's fire strategy.

Speech privacy

Partner offices and the boardroom needed real acoustic separation. Conversations about clients must not be audible in the corridor. This affected partition specification, door seals, ceiling details and even the position of air-conditioning return grilles.

Old services in the existing office

Opening the ceilings in the original office revealed a mix of old fittings, abandoned cables and some fan coil units at the end of their working life. The scope had to be adjusted without delaying the phased program.

Approvals and permits

DIFC has its own fit-out approval process run through the center's authority, alongside the building's landlord requirements. In general terms, the steps were:

  • Landlord technical review and NOC for both the new unit and the refurbishment, including works method statements, insurance and a works schedule showing after-hours activities.
  • Fit-out approval through the DIFC process, with drawings prepared and stamped by a licensed consultant, covering architectural, MEP and fire and life-safety changes, including the opening in the party wall.
  • Fire and life-safety review in line with Dubai Civil Defence requirements, with inspections before the joined space was occupied.
  • DEWA load confirmation for the additional distribution board in the new unit.

Because requirements and fees change, we confirmed the current checklist with the authority and building management before submitting, and allowed time in the program for one round of comments.

Design approach

The firm wanted a calm, confident office that felt established without looking dated. The design used:

  • A clear arrival sequence: a new reception desk in walnut veneer, a waiting area with a view to the boardroom but no view into working areas, and a client washroom accessible without passing lawyers' desks.
  • Separated client and staff zones: boardroom, meeting rooms and reception on the client side; partner offices, associates and the file room behind a controlled door.
  • Glass with privacy: partner offices had glass fronts for daylight, with a frosted band at seated eye level and blinds integrated in the double glazing.
  • A neutral, durable palette: warm gray carpet, white walls, walnut joinery and brushed bronze ironmongery.

Scope of work

  • Full fit-out of the 320 m² adjoining unit: partitions, ceilings, flooring, joinery, MEP and fire services.
  • Removal of part of the party wall and formation of a new structural opening with lintel, under the consultant's design.
  • New reception area and client waiting lounge.
  • New boardroom for 16 with video conferencing containment, acoustic wall panels and a joinery credenza with hidden AV cabinet.
  • Six new partner offices and refurbishment of eight existing ones.
  • Secure file room with a solid-core door, access control and fire-rated storage cabinets supplied by the client.
  • Replacement of carpets, ceilings and lighting in the existing office; repainting throughout.
  • Replacement of four old fan coil units and rebalancing of the air distribution.
  • New data cabling in the new unit and patching into the existing comms room.
  • Pantry upgrade with new worktops, a boiling and chilled water tap, and new cabinets.

Materials and finishes

ElementSpecificationPurpose
Partner office partitionsDouble-skin gypsum with acoustic insulation, taken up to the slabStops sound traveling over the ceiling
Office frontsDouble-glazed partitions with integrated blinds and frosted bandDaylight with privacy on demand
DoorsSolid-core timber doors with drop seals and perimeter sealsAcoustic performance at the weakest point
FlooringCommercial carpet tiles with acoustic backing; porcelain in pantryQuiet corridors, easy replacement
Reception and boardroomWalnut veneer joinery, fabric-wrapped acoustic panelsProfessional finish, controlled echo for video calls
CeilingsGypsum with access panels in offices; acoustic tiles in open areasClean look with service access
PaintLow-VOC washable emulsionLow odor for overnight work before occupied days

Low-odor materials were important: anything applied at night had to be dry and odor-free by 8 am. We used low-VOC paints and adhesives and ran the AC with extra fresh air during curing.

MEP highlights

  • Acoustic-aware HVAC: return air paths for partner offices used lined cross-talk attenuators instead of open grilles, so the air system did not become a path for conversations.
  • Fan coil replacement: four old units in the existing office were replaced with quieter, more efficient units, each with a local thermostat.
  • Lighting: LED panels and downlights with dimming in the boardroom and partner offices; presence detection in the file room and washrooms.
  • Fire services: sprinkler heads and smoke detectors adjusted for the new layout, with the joined space treated as one office in the fire alarm zoning after approval.
  • Data and security: new cabling for the expansion, access control on the staff-zone door and file room, and CCTV coverage of the entrance only, as agreed with the firm.

Program and phasing

The firm stayed open throughout. Work was split into four phases:

PhaseWeeksWorkWorking hours
1. New unit1–6Full fit-out of the adjoining unit behind a sealed dust partitionDaytime for quiet work, evenings for noisy work
2. Party wall opening6–7Structural opening, services re-routing, fire stoppingWeekends only
3. Partner offices7–10Partners moved into new offices, existing offices refurbished in pairsNights and weekends
4. Reception and boardroom10–12Reception and boardroom rebuilt while a temporary meeting room was used in the new unitNights and weekends

Each morning, a supervisor walked the released rooms with the office manager at 7:30 am to confirm they were clean, safe and usable. Furniture and boxes were moved by our team, and any file boxes were moved only in sealed containers by the firm's own staff. Contractor staff signed confidentiality undertakings, and no photographs were taken inside occupied rooms.

Handover

Each phase was handed over separately, with snagging done before the rooms were returned to use. The final handover pack included as-built drawings, authority completion documents, warranties for fan coils, glazing and joinery, and a maintenance schedule for the acoustic door seals, which wear with use and are often overlooked.

Results

  • The firm never closed, and no hearing or client meeting had to be moved because of the works.
  • The new boardroom is used for mediation sessions and video hearings, with clear sound on calls.
  • Speech privacy between partner offices was tested at handover with a simple voice test and met the firm's expectations.
  • The joined office now has one reception, one client route and a secure staff zone.

Lessons learned

  • Daily room lists beat fixed schedules: in a law firm, the plan for the night is only final at 5 pm.
  • Acoustics fail at the details: full-height partitions are wasted if doors lack seals or the return air path is open. Treat the room as a system.
  • Expect surprises in old ceilings: we now include an allowance for replacing aged services in every refurbishment of an office over eight years old.
  • Temporary meeting rooms keep clients happy: setting up a temporary boardroom in the new unit before demolishing the old one avoided disruption.

Key takeaways

  • A live refurbishment in DIFC is possible with careful phasing, night work and a strict daily handover routine.
  • DIFC fit-out approvals run alongside landlord requirements; build time for comments into the program.
  • For law firms, acoustic privacy and confidentiality procedures matter as much as finishes.
  • Indicative 2026 budgets for a mid-to-high specification office refurbishment in DIFC are often in the AED 300–550 per sq ft range, depending on scope, MEP replacement and joinery. Phasing and night work add cost compared with an empty site.

Expanding or refurbishing an office in DIFC?

FIXORA Decor plans and delivers office refurbishments for professional firms that cannot close. Share your floor plan and the dates you cannot be disrupted, and we will propose a phasing plan and an indicative budget. Contact us through our contact page or on WhatsApp at +971501962136.