Luxury Apartment Makeover — Dubai Marina
Luxury apartment makeover in Dubai Marina: a dated 1,850 sq ft two-bedroom reimagined in six weeks with an open-plan kitchen, custom built-in storage, a feature LED wall, layered lighting, full repaint and SPC flooring.
Quick answer
Luxury apartment makeover in Dubai Marina: a dated 1,850 sq ft two-bedroom reimagined in six weeks with an open-plan kitchen, custom built-in storage, a feature LED wall, layered lighting, full repaint and SPC flooring. Together, these items change how an apartment feels rather than just how it looks.
Key facts
- Item Detail Location Dubai Marina Property 2-bedroom apartment Area 1,850 sq ft Client Private homeowner Duration 6 weeks Completed November 2025 Scope of work
Last updated:
Before & after


This luxury apartment makeover in Dubai Marina turned a dated two-bedroom apartment into a bright, open-plan home with custom joinery, layered lighting and a feature LED wall. Over six weeks, FIXORA Decor redesigned the kitchen as an open-plan space, added custom built-in storage, built a lit feature wall, repainted throughout and laid new SPC flooring across the 1,850 sq ft home for a private homeowner.
Below you will find the project details, followed by practical guidance for Dubai Marina owners considering a similar makeover: how the work is usually sequenced in a tower, what approvals to expect, which materials suit a marina-front apartment, and what drives the budget.
Project at a glance
| Item | Detail |
|---|---|
| Location | Dubai Marina |
| Property | 2-bedroom apartment |
| Area | 1,850 sq ft |
| Client | Private homeowner |
| Duration | 6 weeks |
| Completed | November 2025 |
Scope of work
- Open-plan kitchen redesign
- Custom built-in storage
- Feature wall with LED lighting
- Full repaint and new SPC flooring
Together, these items change how an apartment feels rather than just how it looks. Opening the kitchen connects cooking and living spaces and lets daylight travel further into the plan. Built-in joinery removes clutter and freestanding furniture. Layered lighting, including the feature wall, gives the home a different character in the evening. A single continuous floor and a fresh paint scheme tie everything together.
What an open-plan kitchen redesign involves in a Marina tower
Many Dubai Marina apartments were handed over with closed or semi-closed kitchens. Opening them up is one of the most requested upgrades in the area, but in a tower it needs careful planning:
- Checking the wall first. Before any wall is removed, its role must be confirmed. Some walls contain services, and some may be structural or form part of a fire-separation strategy. Drawings and building management guidance come first.
- Ventilation and smells. An open kitchen spreads cooking smells and heat into the living area. A well-specified extract hood and sensible appliance placement matter more than in a closed kitchen. Our guide to open-plan vs closed kitchens covers the trade-offs.
- Services. Moving a sink or cooker can involve drainage falls, water supply and electrical circuits. Keeping wet points close to their original positions usually saves time and approval effort.
- Fire safety. Detectors and sprinklers may need to be repositioned when layouts change. This is coordinated with building management and, where required, the relevant authority.
Custom joinery that earns its space
Built-in storage is what makes an open-plan apartment stay tidy. Fitted units can use the full wall height, fill awkward corners and integrate appliances, media equipment and lighting. On projects like this, joinery is typically designed and measured on site after any demolition, then manufactured off-site while other trades continue, and installed after painting is mostly complete.
For marina-front apartments, material choice matters. Air conditioning runs most of the year and humidity can be high when windows or balcony doors are opened, so moisture-resistant boards near the kitchen and good-quality hardware are worth the investment. Our guide to cabinet materials for UAE humidity explains the options, and our joinery and carpentry service covers what we build.
Layered lighting and the feature LED wall
Good lighting is planned in layers rather than relying on a grid of ceiling downlights:
- Ambient light for general use, often from recessed downlights or cove lighting in a gypsum ceiling.
- Task light where you cook, read or work, such as under-cabinet strips in the kitchen.
- Accent light to highlight a feature, such as an LED-lit wall, shelving or artwork.
A feature wall with integrated LED lighting acts as a focal point for the living area. When planning one, think about color temperature (warm white usually suits living spaces), dimming, access to the LED driver for future maintenance, and how the lighting looks in photographs and at night against the marina view. Our article on lighting layers and color temperature goes into detail.
Why SPC flooring suits Dubai apartments
SPC (stone plastic composite) is a rigid vinyl click flooring that has become popular in Dubai apartments. It is water resistant, dimensionally stable in air-conditioned interiors, warmer underfoot than tile and relatively quiet when fitted with a suitable underlay. It can often be laid over existing level tiles, which reduces demolition, dust and noise in a tower. Building management may set rules on acoustic underlay, so check before you choose.
As a typical / indicative 2026 range, SPC flooring is around AED 60–130 per m² installed, depending on product and floor preparation, confirmed after a site survey. Compare options in our guide to SPC vs LVT vs laminate, or browse SPC vinyl click flooring in our shop.
A paint scheme that keeps the space bright
A full repaint is often the least expensive part of a makeover but has a large effect on the result. In Dubai Marina, strong daylight from the water and floor-to-ceiling glazing can make colors look very different from the sample card, so test patches on more than one wall are worth the time. Owners aiming for a bright, open feel usually do well with:
- One warm neutral for walls across the open-plan area, so the kitchen and living spaces read as one room
- A flat white ceiling to bounce light and hide minor imperfections
- A washable finish in the kitchen zone and hallways, where marks are most likely
- Any stronger color reserved for the feature wall or a single accent area
Our guide to color palettes in Dubai light and painting service explain finishes in more detail.
Living in during the works or moving out?
An open-plan kitchen redesign means no working kitchen for part of the program, and strip-out and flooring create dust and noise across the whole apartment. For a makeover touching every room, most owners find it easier to stay elsewhere, which also lets the contractor work without moving furniture around each day. If you do stay, ask for the bedrooms to be protected and finished first, and agree a weekly plan so you know which rooms are out of use.
How a six-week apartment makeover is typically sequenced
- Design and approvals. Agree layout, joinery and lighting design; submit the renovation application to building management and obtain any NOC required.
- Protection and strip-out. Protect lifts, corridors and retained finishes, then remove the old kitchen and any walls approved for removal.
- First-fix services. Adjust plumbing, electrical circuits and lighting points, including feeds for the feature wall.
- Ceilings and walls. Gypsum work for ceilings and cove lighting, wall repairs and the feature wall build.
- Painting. Preparation and first coats before joinery arrives.
- Flooring. SPC laid once wet trades are finished.
- Joinery and kitchen installation. Fitted units, worktops and appliances.
- Second fix, final coats and snagging. Light fittings, LED commissioning, final paint, deep clean and handover.
Approvals for Dubai Marina renovations
Every tower in Dubai Marina has its own building management or owners' association, and most require an application before any renovation work starts. Cosmetic work such as painting and flooring is usually straightforward, while removing walls or relocating plumbing can need drawings, a master developer NOC or authority approval. Working hours, lift bookings, debris removal and security deposits are also set by the building. Check current requirements with your building management before committing to dates. Our article on apartment renovation rules in Dubai towers explains the typical process.
What drives the budget
As a typical / indicative 2026 guide used on our site, a full one or two-bedroom renovation in Dubai Marina or JBR is around AED 70,000–180,000 excluding 5% VAT, depending on scope and finishes and confirmed after a site survey. See our Dubai Marina and JBR renovation cost guide. The main cost drivers are:
| Factor | Effect on budget |
|---|---|
| Kitchen layout changes | Moving wet points or removing walls adds services work and approvals |
| Joinery extent and finish | Full-height, lacquered or veneered units cost more than standard laminates |
| Lighting design | Cove lighting, feature walls and dimming add gypsum and electrical work |
| Flooring product | Thicker SPC with better wear layers and acoustic underlay costs more |
| Building rules | Restricted hours and lift bookings extend programs |
Planning checklist for Marina owners
- Get your building's renovation rules and application form before design is finalized.
- Confirm which walls can be removed before you fall in love with a layout.
- Plan storage room by room before choosing furniture.
- Design lighting in layers and decide where drivers and switches go.
- Choose flooring that meets building acoustic rules.
- Ask for a 3D visual to check proportions and finishes; see our interior design and 3D visualization service.
- Agree a program with clear milestones for strip-out, joinery delivery and handover.
For a comparable project in a nearby district, see our Business Bay apartment full renovation.
Key takeaways
- Opening the kitchen, adding built-in storage and layering light transform a dated apartment.
- Wall removal in a tower needs checks and building approval first.
- Joinery is measured after strip-out and installed late in the program.
- SPC flooring suits air-conditioned Dubai apartments and reduces demolition.
- Building rules shape the program as much as the design does.
Frequently asked questions
How long does a two-bedroom apartment makeover take in Dubai Marina?
This 1,850 sq ft makeover took six weeks. Timelines depend on scope, joinery lead times and the building's working hours and approval process.
Can I remove the kitchen wall in my Dubai Marina apartment?
Often yes, but only after confirming the wall is not structural and does not contain services that cannot move, and after approval from building management and, where required, the master developer or relevant authority.
Is SPC flooring good for Dubai apartments?
Yes, SPC is water resistant, stable in air-conditioned interiors and can often be laid over existing tiles. Check your building's acoustic underlay requirements first.
Do I need a permit to renovate an apartment in Dubai Marina?
Most towers require a renovation application to building management. Layout or services changes may also need a developer NOC or authority approval.
What is a feature LED wall?
It is a wall designed as a focal point, often with panels, shelving or recesses, with integrated LED lighting to add accent light and atmosphere in the evening.
Start your Dubai Marina makeover
If your apartment feels dated, FIXORA Decor can survey it, design the layout, joinery and lighting, and manage approvals and works through to handover. Call +971 50 196 2136, message us on WhatsApp at +971501962136, or request a quote. You can also explore our turnkey fit-out and renovation and flooring services.
Gallery
Frequently asked questions
An open-plan kitchen redesign means no working kitchen for part of the programme, and strip-out and flooring create dust and noise across the whole apartment. For a makeover touching every room, most owners find it easier to stay elsewhere, which also lets the contractor work without moving furniture around each day. If you do stay, ask for the bedrooms to be protected and finished first, and agree a weekly plan so you know which rooms are out of use.
This 1,850 sq ft makeover took six weeks. Timelines depend on scope, joinery lead times and the building's working hours and approval process.
Often yes, but only after confirming the wall is not structural and does not contain services that cannot move, and after approval from building management and, where required, the master developer or relevant authority.
Yes, SPC is water resistant, stable in air-conditioned interiors and can often be laid over existing tiles. Check your building's acoustic underlay requirements first.
Most towers require a renovation application to building management. Layout or services changes may also need a developer NOC or authority approval.