Project Timeline for a 5,000 sqft Office Fit-Out in Dubai

A week-by-week timeline for a 5,000 sqft office fit-out in Dubai: design, approvals, long-lead procurement, construction, inspections and move-in, plus what extends the program and how to protect your date.

Updated 13 Oct 20267 min read
Project Timeline for a 5,000 sqft Office Fit-Out in Dubai
In this article

Quick answer

A week-by-week timeline for a 5,000 sqft office fit-out in Dubai: design, approvals, long-lead procurement, construction, inspections and move-in, plus what extends the programme and how to protect your date. Shell and core units, heavy MEP changes, premium imported finishes and summer or Ramadan working patterns push the timeline longer.

Key facts

  • 5,000 sqft (about 465 m²) net internal area on a Cat A floor in a Grade A tower
  • Project timeline for a 5,000 sqft office fit-out in Dubai: overview
  • Phase Weeks Key outputs 1.
  • Furniture, IT and move-in 20 – 22 Furniture installed, network live, team moves in Week by week: pre-construction
  • Weeks 1–2: brief and survey
  • Weeks 2–4: concept and budget

Last updated:

A 5,000 sqft office fit-out in Dubai on a Category A floor typically takes about 16 to 22 weeks from signed lease to move-in: around 4 to 6 weeks for briefing and design, 2 to 6 weeks for landlord and authority approvals (partly overlapping with procurement), 8 to 12 weeks of construction and 1 to 3 weeks for inspections, snagging and IT setup. Shell and core units, heavy MEP changes, premium imported finishes and summer or Ramadan working patterns push the timeline longer.

This article sets out a realistic, week-by-week project timeline for a 5,000 sqft office fit-out in Dubai, based on a typical mid-range scope in Business Bay, JLT, Dubai Marina, Al Barsha or Dubai Silicon Oasis. It is a planning guide, not a guarantee; every building and approval route is different. For general durations across project types, see our article on fit-out timelines and what to expect.

The example project

To make the timeline concrete, we assume:

  • 5,000 sqft (about 465 m²) net internal area on a Cat A floor in a Grade A tower
  • About 40 to 45 workstations, a reception, a boardroom, three meeting rooms, two phone booths, four private offices, a pantry with seating, a comms room and storage
  • Glass partitions for meeting rooms, gypsum partitions for offices, feature ceiling at reception and boardroom, carpet tiles and vinyl in the pantry
  • Modifications to fan coil units, diffusers, sprinklers and fire alarm for the new rooms
  • Mid-range catalog furniture with a bespoke reception counter
  • Video conferencing in the boardroom and two meeting rooms

Project timeline for a 5,000 sqft office fit-out in Dubai: overview

PhaseWeeksKey outputs
1. Brief, survey and test-fit1 – 2Brief, measured survey, space plan options
2. Concept and budget2 – 4Approved layout, mood boards, budget estimate
3. Detailed design and pricing4 – 6Construction drawings, MEP and fire drawings, BOQ, contract
4. Landlord and authority approvals6 – 10Landlord no-objection, authority and Civil Defence approvals, permit to work
5. Procurement of long-lead items6 – 14Glass, joinery, furniture, AV, lighting ordered and delivered
6. Construction9 – 19Partitions, MEP, ceilings, finishes, joinery, flooring
7. Testing, inspections and handover19 – 21Civil Defence inspection, landlord sign-off, snagging, handover
8. Furniture, IT and move-in20 – 22Furniture installed, network live, team moves in

Week by week: pre-construction

Weeks 1–2: brief and survey

  • Kick-off meeting with management, HR, IT and facilities
  • Headcount and growth plan, work-style survey, meeting room needs
  • Measured survey of the unit, photos of existing services, review of the landlord's fit-out manual
  • First test-fit layouts

Weeks 2–4: concept and budget

  • Layout refined and approved, ideally by one decision-maker
  • Concept design with materials, colors and 3D views of reception and boardroom
  • Budget estimate and value engineering options
  • Early decisions on long-lead items such as glass partitions and the reception counter

Weeks 4–6: detailed design and contract

  • Construction drawings: partitions, ceilings, flooring, joinery, finishes
  • MEP and fire drawings, prepared by engineers familiar with the building
  • BOQ and fixed price, contract signed, program agreed
  • Furniture and AV selections finalized

Week by week: approvals and procurement

Weeks 6–10: approvals

Approvals usually start with the landlord's technical review, which may involve comments and a resubmission. Authority approval through Dubai Municipality or the relevant free zone authority, and Civil Defence approval for fire systems, follow or run in parallel depending on the building. Durations and fees vary, so confirm the current process for your zone. Typical delays come from incomplete drawings, building-specific requirements and resubmissions. Starting early and using a team experienced with the building saves weeks.

Weeks 6–14: procurement

ItemTypical lead time in Dubai
Framed glass partitions and doors4 – 8 weeks after shop drawing approval
Bespoke joinery (reception, pantry, storage)4 – 8 weeks
Catalog office furniture, stock items2 – 4 weeks
Imported furniture or special finishes8 – 14 weeks
Carpet tiles, stock ranges1 – 3 weeks
Decorative and specification lighting3 – 10 weeks
AV and video conferencing equipment2 – 6 weeks

Lead times change with supplier stock and shipping, so ask for confirmed dates at order. Long-lead items should be ordered as soon as drawings and samples are approved, even if approvals are still pending, provided the risk of design change is low.

Week by week: construction

Weeks 9–10: mobilization and setting out

  • Permit to work issued, site protection installed, hoarding if required
  • Setting out of partitions on the floor, checked against drawings
  • Removal of Cat A ceiling tiles and carpet where needed

Weeks 10–13: partitions and first fix

  • Gypsum partitions framed and insulated
  • First-fix electrical, data containment, and HVAC modifications: relocating fan coil units, new ductwork and diffusers
  • Sprinkler and fire alarm modifications
  • Plumbing for the pantry

Weeks 13–16: ceilings, boarding and wet trades

  • Partitions boarded and taped; feature ceilings built at reception and boardroom
  • Ceiling tiles reinstated in open areas
  • Pantry tiling and splashback
  • Painting starts with first coats

Weeks 16–18: finishes and installation

  • Glass partitions installed
  • Joinery delivered and fitted
  • Second-fix electrical: lighting, sockets, floor boxes
  • Carpet and vinyl laid after wet trades and dusty work finish
  • Final paint coats, manifestation film on glass

Weeks 18–19: commissioning

  • AC testing and balancing for each room
  • Fire alarm and sprinkler testing
  • Electrical testing, lighting controls, emergency lighting
  • AV installation and testing

Weeks 19–22: inspections, snagging, furniture and move-in

  • Civil Defence and landlord inspections; book them early as availability varies
  • Snagging walk with the client, contractor fixes items within agreed days
  • Deep cleaning
  • Furniture delivery and installation
  • Network, Wi-Fi, printers and access control configured
  • Move-in, usually over a weekend

Who does what: roles and responsibilities

A clear responsibility matrix keeps the timeline moving. On a typical 5,000 sqft project:

TaskClientFit-out contractorLandlord / building
Brief, headcount, budget approvalLeadsAdvises-
Design and drawingsApprovesPreparesReviews against fit-out manual
Authority and Civil Defence submissionsSigns where requiredPrepares and follows upProvides NOC
Insurance and permit to work-Provides certificatesIssues permit
IT, telecom line and access controlLeads or appoints IT vendorProvides containment and powerCoordinates riser access
FurnitureApproves selectionSupplies or coordinatesService lift booking
Inspections and handoverAttends snaggingBooks and managesFinal inspection and sign-off

Two client-side tasks are often forgotten until the last month: the telecom connection, which can take weeks to activate, and the move logistics, including the removal company, the service lift booking and notice to your current landlord. Start both by the middle of construction.

A faster alternative: phased or partial occupancy

If your move date cannot move, ask whether the building allows phased occupancy. For example, the open-plan workstations and toilets can be completed first while the boardroom and feature reception finish a week or two later. This needs careful planning with the landlord and Civil Defence, because occupied areas must have working fire systems and safe exits, but it can protect a hard move-in date without paying for night shifts across the whole project.

Budget context for the timeline

As an indicative 2026 range, a mid-range Cat B fit-out of this size costs roughly AED 1.25 to 2 million excluding VAT, furniture and IT, depending on specification and MEP changes. Shortening the program with extended working hours, overtime and express deliveries is possible, but it adds cost. In most cases, early decisions save more time than money spent on acceleration.

What makes the timeline longer

  • Shell and core handover: add roughly 4 to 8 weeks for Cat A works.
  • Late layout changes: every change after approvals can trigger resubmission.
  • Heavy MEP changes: server rooms, extra kitchens or showers need more design and approval time.
  • Restricted working hours: some towers limit noisy work to evenings or weekends.
  • Ramadan: shorter working hours on many sites reduce productivity.
  • Summer: deliveries and outdoor works are slower; many decision-makers travel, delaying approvals.
  • Imported items: shipping delays can hold up handover.

How to protect your move-in date

  • Align the program with your lease's rent-free period and notice on your current office.
  • Appoint one decision-maker with authority to approve designs and samples quickly.
  • Freeze the layout before approvals are submitted.
  • Order long-lead items early, and choose stock items where the date matters.
  • Ask for a weekly progress report with a two-week look-ahead and a list of decisions needed.
  • Build in a buffer of two to three weeks before your hard move-in date.

One more practical tip: hold a short weekly site meeting with photos and a single updated program, even if everything looks on track. Problems such as a delayed glass delivery or a landlord comment on the fire drawings are far easier to absorb when they are spotted three weeks before handover rather than three days. Ask the contractor to flag every decision you owe them, with the date it is needed, so your own approvals never become the cause of a delay.

Key takeaways

  • Plan about 16 to 22 weeks for a 5,000 sqft Cat A office fit-out from lease to move-in.
  • Approvals and long-lead items, not construction, usually set the critical path.
  • Freeze the design early and order long-lead items as soon as possible.
  • Expect shell and core, heavy MEP, Ramadan and summer to extend durations.
  • Keep a buffer before your move-in date.

Plan your office move with confidence

FIXORA Decor prepares a detailed program for every office fit-out in Dubai, mapped to your lease dates and updated weekly. Request a program and quote or contact our team on WhatsApp at +971501962136.

The information in this article is general guidance, not advice for your specific project. See our Terms.

Frequently asked questions

About 16 to 22 weeks from signed lease to move-in for a Cat A floor with a mid-range scope, including design, approvals, 8 to 12 weeks of construction and inspections. Shell and core units take longer.
Approvals and long-lead items such as glass partitions, bespoke joinery and imported furniture. Construction itself is often not the limiting factor.
Generally no. Most buildings will not issue a permit to work until landlord and required authority approvals are in place. Procurement of low-risk items can start earlier.
Yes. Shorter working hours on many sites reduce productivity, so allow extra time if your program runs through Ramadan.
Freeze the layout early, appoint one decision-maker, choose stock items for long-lead elements and use a contractor experienced with your building's approval process.

Sources

Was this article helpful?

Get new articles by email

Practical tips now and then. Confirm by email, unsubscribe any time.

Need help with your project?

Our team is ready to help — get a free quotation today.

Or call us+971 50 196 2136

Serving