Quick answer
How to plan a hotel apartment refurbishment in Dubai: phasing around occupancy, mock-up units, durable finishes, procurement lead times, guest disruption and typical costs per key. Refurbishing hotel apartments in Dubai is a balancing act between upgrading the product and protecting revenue.
Key facts
- Furniture, fixtures and equipment for dozens of identical rooms are usually manufactured to order, with lead times of 8–16 weeks, plus shipping if imported.
- Building in spare stock for damaged items and future maintenance, typically 3–5% of quantities.
- A contingency of 7–10% is sensible on hard refurbishments, because older buildings often reveal hidden issues once finishes are removed.
Last updated:
Refurbishing hotel apartments in Dubai is a balancing act between upgrading the product and protecting revenue. Most operators cannot close a whole building, so works are phased floor by floor while guests stay elsewhere in the property. A successful program depends on a tested mock-up unit, finishes that survive heavy use, procurement that delivers on time, and strict control of noise, dust and access. Soft refurbishments of furniture, fabrics and decoration typically cost AED 25,000–70,000 per key, while full refurbishments including bathrooms and kitchens commonly range from AED 90,000 to AED 250,000 per key, exclusive of 5% VAT.
Define the scope: soft, hard or full
Be clear early about what level of refurbishment you are planning, because it drives budget, program and approvals:
- Soft refurbishment: loose furniture, mattresses, curtains and blinds, carpets, painting, artwork and minor lighting changes. Rooms can often be turned around in days.
- Hard refurbishment: new flooring, bathrooms, kitchenettes, fixed joinery, ceilings and lighting. Rooms are out of service for several weeks.
- Full refurbishment: includes MEP upgrades such as AC units, plumbing risers, electrical distribution and fire and life safety systems, and may need wider authority approvals.
A condition survey of a sample of units, plus a review of maintenance records, helps decide where the real problems are. Leaking bathrooms or failing AC units should be fixed before money is spent on finishes.
Phasing around occupancy
Phasing is the core of the plan. Typical approaches:
- Floor by floor: close one or two floors at a time, keeping noisy work vertically separated from occupied floors where possible.
- Stack by stack: work on vertical stacks of rooms when riser replacement is needed.
- Seasonal timing: schedule the heaviest phases in the quieter summer months, when occupancy is usually lower, accepting the midday outdoor work break from 15 June to 15 September for any external works.
Agree with the operator the working hours for noisy activities, the dedicated service lift for contractors, protection of corridors and lifts, and a clear process for guest complaints. Dust screens, negative pressure in work areas and daily cleaning of shared routes are essential. Fire and life safety systems must remain operational in occupied areas throughout, with any temporary changes agreed with Dubai Civil Defence and the building's fire safety team.
The mock-up unit
Before committing to the full program, refurbish one unit, or one of each unit type, as a mock-up. It tests the design, reveals hidden conditions, establishes real durations, and lets the operator see and approve finishes. Common discoveries include uneven screeds, old pipework that needs replacing, or furniture that does not fit through doors. Budget two to four weeks for the mock-up and a further one to two weeks for revisions.
Keep the approved mock-up as the reference standard for the whole project. Photograph every detail, record the approved samples, and use the room to train installation crews so quality stays consistent from the first floor to the last. Where the operator has brand standards, invite their representative to inspect the mock-up before sign-off rather than at the end.
Finishes durability
Hotel apartments see more wear than homes: luggage, frequent turnovers, long stays with cooking, and daily cleaning. Specify for durability:
| Element | Durable specification | Why |
|---|---|---|
| Flooring | Porcelain tiles or commercial luxury vinyl (heavy-duty wear layer) | Resists scratches, water and cleaning chemicals |
| Carpet (bedrooms) | Solution-dyed nylon, contract grade | Colourfast and cleanable |
| Walls | Scrubbable washable paint; vinyl wallcovering in corridors | Easy to touch up, resists scuffs |
| Kitchenette | Quartz or compact laminate tops; moisture-resistant carcasses | Handles heat and spills |
| Bathrooms | Large-format porcelain, epoxy grout, frameless screens with sturdy hardware | Fewer joints, less maintenance |
| Fabrics | Contract-grade, flame-retardant, UV-resistant | Safety and resistance to fading in strong sun |
Corner guards, kick plates, wall bumpers behind luggage racks and robust door hardware add little cost and extend the life of the refurbishment considerably. If the refurbishment includes a lobby café or breakfast counter, our guide to small café design and fit-out covers layout and approvals.
Procurement and lead times
Procurement often drives the program more than site work. Furniture, fixtures and equipment for dozens of identical rooms are usually manufactured to order, with lead times of 8–16 weeks, plus shipping if imported. Good practice includes:
- Approving samples and the mock-up before placing bulk orders.
- Ordering long-lead items such as joinery, sanitaryware and lighting in batches aligned with phases.
- Arranging secure storage on or near site, because hotel back-of-house areas are rarely large enough.
- Building in spare stock for damaged items and future maintenance, typically 3–5% of quantities.
- Clear labeling and room-by-room packing lists to speed installation.
Guest experience and handover
Protecting guests during works
Guests who book a hotel apartment do not expect to share a corridor with a refurbishment. Reviews can suffer quickly if noise, dust or contractors are visible. Practical measures include:
- Clearly defined work zones with full-height, fire-rated hoarding and signage, and separate contractor access via service lifts and stairs.
- Quiet hours agreed with the operator, typically restricting drilling, breaking and cutting to late morning and afternoon.
- Off-site preparation: cutting, joinery assembly and furniture unpacking done in a workshop or a dedicated floor rather than next to guest rooms.
- Daily cleaning of shared corridors, lifts and lobbies, and floor protection along delivery routes.
- A single point of contact for the front office team to report guest complaints, with a same-day response.
- Pre-arrival messages and front desk briefings so guests know what to expect and are allocated quiet rooms.
Handover, snagging and maintenance
Refurbished rooms should return to inventory only after a thorough inspection by both the contractor and the operator's team. Use a room-by-room checklist covering finishes, furniture, AC performance, plumbing, lighting, door locks, safes and televisions, and test each room before housekeeping does its final clean. Collect warranties, maintenance manuals and spare stock, and brief the engineering team on new equipment. A short planned maintenance routine for silicone joints, grout, door closers and AC filters keeps the refurbished rooms in condition much longer.
Approvals and budgets
Approvals and building management
Soft refurbishments usually need only building management approval. Hard and full refurbishments typically need fit-out approvals from Dubai Municipality or the relevant zone authority, Dubai Civil Defence approval for changes affecting fire safety, and possibly Department of Economy and Tourism inspections if room categories or facilities change. Fees apply. Build approval durations into the phasing plan rather than treating them as a one-off at the start.
Budgeting per key
Operators usually budget refurbishments per key, which makes comparison across unit types and properties easier. Break the budget into clear packages: furniture, fixtures and equipment; finishes and joinery; bathrooms and kitchenettes; MEP upgrades; public area works; professional fees; and contingency. A contingency of 7–10% is sensible on hard refurbishments, because older buildings often reveal hidden issues once finishes are removed. Remember to include temporary revenue loss from closed rooms in the business case, alongside the expected uplift in rates and reviews after completion.
What to watch out for
- Skipping the mock-up and discovering problems across fifty rooms.
- Choosing residential-grade finishes that wear out within a year.
- Ordering furniture before confirming door widths and lift sizes.
- Poor guest communication about noise and closed areas.
- Leaving MEP problems in place under brand new finishes.
FIXORA Decor plans hospitality refurbishments around the operator's occupancy forecasts, with a fixed turnover rate per week so revenue managers know exactly which rooms will be available.
Next step
Share your unit mix, occupancy pattern and refurbishment goals, and FIXORA Decor will prepare a phasing plan and budget per key. Request a free quotation or see our turnkey fit-out service for hospitality projects.
The information in this article is general guidance, not advice for your specific project. See our Terms.