In this article
Quick answer
Plan a kitchen renovation in Dubai: layouts, cabinetry materials, worktops, moving plumbing and power, building approvals, typical costs and a realistic timeline. The cost and timeline depend on three decisions: whether the layout changes, what the cabinets and worktops are made of, and whether plumbing, drainage, gas or extraction need to move.
Key facts
- Survey, design and finalising cabinet drawings: 1–3 weeks.
- Approvals and cabinet manufacture, running in parallel: 3–6 weeks.
- Strip-out and first-fix plumbing and electrical: 3–5 days.
- Wall and floor tiling, ceiling and paint: 1–2 weeks.
- Cabinet installation and templating of worktops: 3–5 days.
- Worktop fabrication and fitting: 1–2 weeks after templating.
Last updated:
A kitchen renovation in Dubai usually takes six to ten weeks from design to handover, of which three to six weeks are on site, and costs typically AED 25,000–60,000 for a mid-range apartment kitchen and AED 60,000–180,000 or more for a large villa kitchen, exclusive of 5% VAT and appliances. The cost and timeline depend on three decisions: whether the layout changes, what the cabinets and worktops are made of, and whether plumbing, drainage, gas or extraction need to move. Settle those early and the rest of the project becomes straightforward.
Choosing the layout
Most Dubai kitchens fall into one of five layouts, and the right choice depends on the room shape, the number of cooks and how open the kitchen is to living areas.
- Single wall: common in studios and one-bedroom apartments in JVC, JLT and Dubai Marina. Efficient but limited in worktop space.
- Galley: two parallel runs. Excellent for working efficiency in narrow apartment kitchens; aim for at least 1.1–1.2 m between runs.
- L-shape: works well in open-plan apartments and townhouses, often with a dining table or small island.
- U-shape: maximum storage and worktop in a closed villa kitchen.
- Island or peninsula: popular in villas in Dubai Hills Estate, Arabian Ranches and Damac Hills. Allow at least 1 m clearance around an island, more where two people cook.
Many Dubai villas have a show kitchen open to the living area and a separate closed kitchen for heavy cooking. Whether to open your kitchen up is a decision with its own trade-offs, which we cover in open-plan versus closed kitchens in Dubai homes.
Cabinetry: carcasses, fronts and hardware
Humidity and heat in the UAE make carcass material important. Moisture-resistant MDF or moisture-resistant particleboard is the minimum standard for carcasses, with marine plywood or aluminum carcasses an option under sinks and in villas where humidity is higher. Edges should be fully sealed with edge-banding, particularly around the sink and dishwasher.
Fronts come in several finishes: high-pressure laminate is durable and affordable, lacquered or painted MDF gives a seamless color, acrylic offers high gloss, and wood veneer or solid timber suits a warmer look but needs more care. Hardware matters as much as the fronts. Specify soft-close hinges and full-extension drawer runners rated for the expected loads, and prefer deep drawers to base cupboards for everyday storage.
Storage planning
Work out storage needs before choosing door styles. List what the kitchen must hold: pots and pans, small appliances, dry goods, crockery, cleaning products and recycling. Then allocate space. Tall larder units with internal drawers make the most of floor area, corner units benefit from pull-out or carousel fittings, and a dedicated bin unit near the sink keeps waste out of sight. In villas with a separate closed kitchen or pantry, bulk storage can move there, freeing the show kitchen for display and daily items. Wall cabinets taken to the ceiling avoid dust-collecting tops and add useful storage for rarely used items.
Lighting and power
Plan lighting in layers: general ceiling lighting, task lighting under wall cabinets to light the worktop without shadows, and accent lighting for glass cabinets or shelving. Choose fittings with a neutral white color temperature, typically around 3,000–4,000 K, and a good color rendering index so food looks natural. Under-cabinet strips should be rated for kitchen use and installed with accessible drivers. Position sockets at worktop level away from the sink and hob, and allow for appliance garages if you want toasters and coffee machines hidden.
Appliances and splashbacks
Decide on appliances before cabinet drawings are finalized. Built-in ovens, microwaves, coffee machines and integrated fridges each need specific opening sizes and ventilation gaps, and an induction hob needs the right worktop cut-out and a dedicated circuit. A tall fridge-freezer housing should allow for the door swing against adjacent walls. For splashbacks, the simplest durable options are porcelain tiles, a continuation of the worktop material, or toughened back-painted glass. Behind a gas hob, check that the chosen material is suitable for heat and keeps the required clearance from the burners.
Worktops
The worktop is usually the most visible single cost. The table below compares common options. Prices are typical installed ranges per linear meter at standard 600 mm depth, exclusive of VAT, and vary with thickness, edge detail and cut-outs.
| Material | Strengths | Watch out for | Typical range (AED per linear m) |
|---|---|---|---|
| High-pressure laminate | Affordable, wide choice of patterns | Heat damage, swollen edges near the sink | 350–800 |
| Solid surface | Seamless joints, integrated sinks, repairable | Can scratch and mark with hot pans | 1,200–2,200 |
| Engineered quartz | Hard-wearing, non-porous, consistent color | Not fully heat-proof; joins visible on long runs | 1,400–3,000 |
| Natural granite | Very durable and heat-resistant | Needs periodic sealing, heavy slabs | 1,200–2,800 |
| Sintered stone or porcelain slab | Heat, stain and UV resistant, thin profiles | Edges can chip; skilled fabrication needed | 1,800–3,800 |
| Marble | Distinctive look | Etches with acids, stains, needs sealing | 2,000–5,000 |
In towers, check that slab lengths fit the service lift before ordering. Long runs may need a joint, which should be planned rather than discovered.
Moving plumbing, power, gas and extraction
Keeping the sink, cooker and fridge in their existing positions is the simplest and cheapest option. Relocating them involves:
- Drainage: waste pipes need a consistent fall to the nearest stack or gully. In apartments this limits how far a sink can move without raising the floor.
- Electrical: ovens, induction hobs and some dishwashers need dedicated circuits. Adding load may require a DEWA-compliant distribution board upgrade.
- Gas: many towers and villas have a central gas supply. Any change to gas pipework must be done by an approved gas contractor and inspected; never as general building work.
- Extraction: ducted cooker hoods vent outside and suit heavy cooking. In many towers external ducting is not permitted, leaving recirculating hoods with carbon filters as the only option.
Approvals
Replacing cabinets and worktops in the same location usually needs only a standard building management or community notification. Moving a kitchen to a different room, relocating drainage, changing gas lines or removing walls requires drawings and formal approval from building management or the developer, and in some cases from Dubai Municipality or Civil Defence. Tenants need the landlord's written consent before any of this.
Timeline
- Survey, design and finalizing cabinet drawings: 1–3 weeks.
- Approvals and cabinet manufacture, running in parallel: 3–6 weeks.
- Strip-out and first-fix plumbing and electrical: 3–5 days.
- Wall and floor tiling, ceiling and paint: 1–2 weeks.
- Cabinet installation and templating of worktops: 3–5 days.
- Worktop fabrication and fitting: 1–2 weeks after templating.
- Appliances, splashback, second-fix and testing: 3–5 days.
FIXORA Decor templates worktops only after the cabinets are fixed and level, which avoids gaps and cracks at the joints.
If the kitchen is your only cooking space, plan how the household will manage for the site period. A temporary set-up with a microwave, a kettle and a small fridge in another room makes three to five weeks far easier, and some families time the work to coincide with travel.
Common mistakes
- Choosing a ducted hood before confirming that the building allows external ducting.
- Too few sockets on the worktop run. Plan for at least four double sockets in an average kitchen.
- Ignoring the working triangle between sink, hob and fridge in a large villa kitchen.
- Ordering appliances after cabinet manufacture, which leads to mismatched openings.
- Standard carcass boards near the sink, which swell within a few years in UAE humidity.
Next step
Send us your kitchen dimensions and a few photos, and FIXORA Decor will prepare a layout proposal and a free quotation. Our joinery and carpentry service manufactures cabinets to measure for apartments and villas across Dubai.
The information in this article is general guidance, not advice for your specific project. See our Terms.