A restaurant fit-out in Dubai is a regulated build, not only an interior project. Before you open, the space needs approved drawings, a kitchen that meets Dubai Municipality food premises requirements, an extraction and fire suppression system accepted by Dubai Civil Defence (DCD), a correctly sized grease trap, and final inspections that lead to your food establishment permit. For a typical 150–300 m² casual-dining unit, plan for around 12–20 weeks from design start to opening and a fit-out budget that typically sits between AED 3,000 and AED 6,500 per m², excluding kitchen equipment and loose furniture.
Start with a unit that can work
Many restaurant projects get into trouble before the first drawing, because the unit was leased without checking whether it can operate as a food outlet. Before you sign, confirm the following with the landlord or building management:
- Permitted use: the unit must be approved for food and beverage, not only retail or office use.
- Exhaust route: a clear path for the kitchen extract duct to roof level or another approved discharge point, away from fresh air intakes and residential windows.
- Drainage: a connection for kitchen waste through a grease interceptor, with space to install and service it.
- Power: enough electrical capacity for cooking lines, cold rooms and air conditioning. A busy kitchen can need several times the load of a shop, and DEWA load upgrades take time.
- Gas: whether the building has a central LPG supply or allows a gas bank, and the landlord's rules for gas works.
- Cooling: whether the chilled water or district cooling supply can cover the extra demand, and what connection and consumption charges apply.
A unit that fails on exhaust or drainage can add weeks and significant cost, or make a full cooking concept impossible. It is worth paying for a short technical survey before the lease is final.
The approvals path
The exact route depends on location. In mainland Dubai, Dubai Municipality reviews food premises layouts and building works, while DCD covers fire and life safety. In free zones and master communities, the zone authority (for example Dubai Development Authority or Trakhees) or the master developer may run the permit process, and malls add their own landlord approval on top. In general, plan for these stages:
- Landlord or mall design approval of the concept and technical drawings.
- Food premises layout review, covering kitchen flow, hand-wash stations, storage, staff facilities and finishes.
- Fit-out permit for interior and MEP works.
- DCD approval of fire alarm and sprinkler modifications, emergency lighting, exit signage and the kitchen hood suppression system.
- Inspections and completion, after which the license activity and food establishment permit can be finalized.
Fees apply at each stage and vary by authority and project size. Requirements change from time to time, so the design team should check current guidelines before submission rather than copying a previous project.
Kitchen design: flow, finishes and hygiene
Food safety inspectors look for a logical one-way flow: goods in, cold and dry storage, preparation, cooking, service, and a separate route for dirty returns and waste. Raw and ready-to-eat preparation should be separated by distance or dedicated zones. Typical expectations include:
- Dedicated hand-wash basins with hands-free taps in preparation areas, separate from food sinks.
- Smooth, impervious and washable wall finishes such as hygienic PVC cladding or full-height ceramic tiling, with coved junctions at floor level.
- Slip-resistant, non-absorbent flooring laid to falls towards floor drains, usually anti-slip ceramic tiles or seamless resin.
- Washable ceilings, typically moisture-resistant tiles or sealed gypsum, with no exposed fibrous insulation.
- Stainless steel worktops and shelving, with equipment on legs or sealed to the floor so it can be cleaned underneath.
- Staff changing area, lockers and toilets that do not open directly onto food areas.
- Insect screening at openings and a pest-proof, ventilated waste store.
Extraction, fresh air and fire suppression
Kitchen ventilation is usually the largest single technical package. The hood captures heat, smoke and grease; the extract duct carries it to discharge; and a make-up air system replaces the air removed so the kitchen does not pull hot air and odors from the dining room. In practice this means:
- Hoods sized to overhang the cooking equipment, with baffle filters staff can remove and wash daily.
- Fire-rated, sealed extract ductwork with access panels for cleaning, enclosed in fire-rated construction where it passes through other areas.
- Smoke and odor control, such as electrostatic precipitators or carbon filtration, where discharge is close to neighbors or inside a mall.
- A wet chemical fire suppression system over the cooking line, linked to automatic gas shut-off and approved by DCD.
- Treated fresh air to the dining area so the space stays comfortable through the summer months.
Budget for professional duct cleaning at regular intervals once you trade; landlords and insurers commonly ask for records.
Grease traps and drainage
Every food outlet needs a grease interceptor on the kitchen waste line before it reaches the public sewer, and Dubai Municipality sets the general requirements. Sizing depends on the number of sinks, dishwashers and expected flow. Under-sink units can suit small cafés with light cooking; full restaurants usually need a larger floor-mounted or below-ground interceptor in an accessible position. Avoid locating the trap where emptying would disrupt food preparation, and plan for regular servicing by an approved waste contractor with records kept on site.
Dining area and front of house
The dining room is where the brand lives, but it still has to meet technical rules. Seating layouts must keep exit routes clear and wide enough for the occupancy, accessible toilets are expected in most new fit-outs, and decorative materials need suitable fire ratings. Choose upholstery, table tops and floor finishes that stand up to daily cleaning chemicals. Acoustic treatment is often overlooked: hard surfaces look clean, but a dining room full of tile, glass and concrete can become uncomfortably loud at peak times.
Typical timeline and cost ranges
| Stage | Typical duration | Notes |
|---|---|---|
| Concept and kitchen layout | 2–4 weeks | The menu drives equipment and layout |
| Technical drawings and approvals | 3–6 weeks | Landlord, authority and DCD comments |
| Fit-out works | 6–10 weeks | Longer for large or complex units |
| Testing, inspections and snagging | 1–3 weeks | Suppression, fire alarm, food premises |
As a guide, a casual-dining fit-out typically costs AED 3,000–6,500 per m² for interiors and MEP, before kitchen equipment, furniture and signage. Kitchen equipment for a full cooking concept commonly adds AED 150,000–500,000 depending on the menu. A café with a light kitchen usually sits lower; see our guide to small café design and fit-out. All figures are typical ranges, exclusive of 5% VAT, and depend on the unit's condition and the landlord's requirements.
What to watch out for
- Ordering kitchen equipment before the layout is approved, then having to change it.
- Discovering late that the extract duct must run through a neighboring unit or shaft you do not control.
- Choosing decorative finishes that are not washable or that stain under heavy use.
- Leaving DEWA load increases and gas approvals until the end.
- Forgetting the landlord's fit-out deposit, consultant fees and authority fees in the budget.
FIXORA Decor coordinates design, approvals and construction in one program, so the kitchen layout, MEP engineering and site works all follow the same set of drawings. That coordination is usually what keeps an opening date realistic.
Next step
If you have a unit in mind or a signed lease, share the floor plan and concept with FIXORA Decor and we will review the technical constraints before you commit to a layout. Request a free quotation or read more about our turnkey fit-out service.
The information in this article is general guidance, not advice for your specific project. See our Terms.