In this article
Quick answer
How to read a fit-out quotation and BOQ in Dubai line by line: a worked sample, quick quantity checks, indicative 2026 rates, provisional sums, exclusions and the questions to send back to contractors. This is a practical, line-by-line walkthrough using a sample BOQ for a two-bedroom apartment renovation in JVC and an office refresh in Business Bay.
Key facts
- Floor removal and new tiles both use 78 m².
- A AED 6,000 allowance for all sanitaryware in a three-bathroom villa is unlikely to be enough for mid-range brands.
- Validity: often 15 to 30 days because material prices change.
- VAT: confirm whether totals are before or after 5% VAT, and that the company's TRN appears on the quote.
Last updated:
To read a fit-out quotation and BOQ in Dubai, check five things in order: the scope and drawings it is based on, the quantities and units, the specification behind each rate, the provisional sums and exclusions, and the commercial terms such as VAT, validity, payment and program. A good BOQ lets you see exactly what you are buying and price changes fairly; a vague one hides the real cost until the project is under way.
This is a practical, line-by-line walkthrough using a sample BOQ for a two-bedroom apartment renovation in JVC and an office refresh in Business Bay. For the basics of what a BOQ is, see our earlier guide on how to read a BOQ quotation; here we focus on reading real line items and spotting what is missing.
How to read a fit-out quotation and BOQ in Dubai: the structure
Most fit-out BOQs in the UAE follow a similar layout:
- Cover and summary: project, date, quote reference, validity period, totals by section, VAT and grand total.
- Preliminaries: site setup, protection, insurance, approvals, supervision, cleaning, debris removal.
- Trade sections: demolition, partitions and ceilings, flooring, wall finishes, joinery, doors, sanitaryware, MEP (electrical, plumbing, HVAC), fire services, specialist items.
- Provisional sums and allowances.
- Exclusions, assumptions and terms.
Every line should have a description, unit (m², lm, no., item, lot), quantity, rate and amount. Lines priced only as "lot" or "item" are not wrong, but they should be the exception, used for things like site setup or AC balancing.
A sample BOQ, read line by line
The extract below is illustrative. Rates are indicative 2026 figures for mid-range work in Dubai, excluding VAT, and real rates depend on brand, quantity and site conditions.
| Ref | Description | Unit | Qty | Rate (AED) | What to check |
|---|---|---|---|---|---|
| 2.01 | Remove existing floor tiles and screed, dispose off-site | m² | 78 | 45 | Does it include debris removal permits and building lift protection? |
| 3.04 | Supply and install 60x120 porcelain floor tile, matte, rectified, with adhesive and grout | m² | 78 | 210 | Tile brand and series, supply rate within the total, wastage allowance |
| 3.05 | Skirting, tile cut, 100 mm | lm | 64 | 45 | Quantity should match room perimeters minus door openings |
| 4.02 | Gypsum board ceiling with 50 mm cove for LED strip | m² | 32 | 120 | Includes access panels? Paint included or in painting section? |
| 5.01 | Kitchen cabinets, high-gloss lacquer, MR MDF carcass, soft-close hardware | lm | 6.5 | 2,400 | Upper and lower included? Worktop separate? Hardware brand? |
| 6.03 | Bathroom waterproofing, cementitious two-coat with 48-hour flood test | m² | 22 | 85 | Floor and wall upturn height; flood test written in |
| 7.10 | New lighting point, wiring from DB, switch | no. | 18 | 180 | Fittings supplied or by provisional sum? |
| 9.01 | Light fittings supply | PS | 1 | 9,000 | Is the allowance realistic for your design? |
What this extract tells you
- Quantities are consistent. Floor removal and new tiles both use 78 m². If the new tile quantity were lower than the demolition quantity, ask why.
- Specifications are specific. "60x120 porcelain, matt, rectified" is better than "floor tiles". Even better is a named product or a supply allowance per m².
- Waterproofing includes a test. In UAE bathrooms, a flood test before tiling is a sign of a careful contractor.
- Fittings are a provisional sum. The final cost will depend on what you choose, so the allowance matters.
Reading quantities: quick checks you can do yourself
- Measure the main rooms with a laser or tape and compare floor areas. A variance under 5 percent is normal; bigger differences need an explanation.
- Count light points, sockets, doors and sanitary fittings on the drawings and compare with the BOQ.
- For joinery priced per linear meter, measure the wall length the units will occupy.
- For painting, quantities are usually measured on wall and ceiling area, not floor area. A typical apartment wall area is roughly 2.5 to 3 times its floor area.
Reading rates: is the price reasonable?
Rates vary with specification and project size, so do not judge one line in isolation. Use these indicative 2026 Dubai ranges for common mid-range items as a sense check, excluding VAT:
| Item | Indicative range (AED) |
|---|---|
| Interior painting, two coats on prepared walls | 12 – 25 per m² |
| Porcelain floor tiles, supply and install | 120 – 300 per m² |
| SPC or laminate flooring, supply and install | 60 – 160 per m² |
| Gypsum ceiling, flat, painted | 70 – 140 per m² |
| Gypsum partition with insulation, both sides finished | 120 – 220 per m² |
| Glass office partition, single glazed, framed | 550 – 1,000 per m² |
| Kitchen cabinets, mid-range | 1,600 – 3,500 per lm |
A rate well below these ranges is not automatically a bargain. It often means a lower specification, a smaller scope than you think, or an intention to recover the margin through variations.
Provisional sums, prime cost and allowances
Provisional sums (PS) cover work that is not fully defined; prime cost (PC) sums cover items to be selected later, such as sanitaryware or lighting. In both cases the actual cost replaces the allowance at the end. Check:
- That each allowance is realistic for the quality you expect. A AED 6,000 allowance for all sanitaryware in a three-bathroom villa is unlikely to be enough for mid-range brands.
- Whether the contractor adds a margin or installation charge on top of the allowance.
- That the total of provisional sums is visible. If a third of the quote is provisional, the price is not really fixed.
Exclusions: where the extra costs hide
Read the exclusions page twice. Common exclusions in Dubai fit-out quotations include:
- Authority, landlord and developer fees and deposits
- Design or engineering drawings for approvals
- Civil Defence system modifications and inspections
- AC balancing, duct cleaning or new AC units
- DEWA load increase applications
- Furniture, curtains, appliances and IT cabling
- Out-of-hours work premiums required by the building
- Final deep cleaning
None of these is unusual on its own. The problem is when one quote includes them and another excludes them, making the second look cheaper. Price the exclusions and add them back to compare like for like.
Commercial terms in the quotation
- Validity: often 15 to 30 days because material prices change.
- VAT: confirm whether totals are before or after 5% VAT, and that the company's TRN appears on the quote.
- Payment terms: advance, milestones, retention or final holdback.
- Program: start and completion dates or a duration in weeks.
- Warranty: workmanship warranty period and how manufacturer warranties are passed on.
- Assumptions: for example "assumes existing AC capacity is adequate" or "assumes no asbestos or hidden defects". Each assumption is a potential variation.
Office example: what changes in a commercial BOQ
For an office refresh in Business Bay, the BOQ grows sections for fire alarm, sprinkler modifications, HVAC diffusers and fan coil relocation, data cabling, access control and AV. Look for:
- Sprinkler and fire alarm modifications priced per head or detector, plus a line for Civil Defence submissions and testing
- HVAC: number of diffusers moved or added, ductwork lengths, and balancing as a separate item
- Glass partitions measured in m² with door sets counted separately, including manifestation film
- Landlord requirements such as nominated subcontractors, which may be marked as provisional
Preliminaries: the section most people skip
Preliminaries are the costs of running the site rather than building anything visible. On a Dubai fit-out they commonly cover the site supervisor and project manager, protection of lifts, corridors and existing finishes, temporary power and lighting, debris removal and skip or chute arrangements, insurance, health and safety equipment, building management requirements and final cleaning. On a small apartment job they may be a few thousand dirhams; on an office fit-out they often run to roughly 5 to 12 percent of the contract value, depending on duration and building rules.
Two warning signs: preliminaries that are near zero, which usually means the costs are hidden in the rates or will appear as variations, and preliminaries that are very high without explanation. Ask for a short breakdown either way. Preliminaries that are tied to the program also tell you something: if the contractor has priced eight weeks of supervision for a job they promised in five, the program may not be realistic.
How the BOQ will be used for variations
The BOQ is not only for the tender. During the project, every change is valued against it. If you add six light points, the contractor should use rate 7.10 from the sample above. If you remove a wall, the omission should be credited at the agreed rate. This is why itemized rates are worth insisting on: they make every change predictable and keep the final account short. Where no matching rate exists, the contract should say that a new rate will be agreed based on similar items before the work starts.
Questions to send back to the contractor
- Which drawings and revision is this quote based on?
- Please confirm brand and series for tiles, sanitaryware, paint and hardware.
- What is included in preliminaries?
- Please price the following exclusions as options.
- What is the basis for each provisional sum?
- How long is the quotation valid, and which rates are most likely to change?
Asking these in writing gives you a clear record and helps bring several quotations onto the same basis.
Key takeaways
- Read the BOQ in order: scope, quantities, specifications, allowances and exclusions, then terms.
- Check quantities against your own measurements and the drawings.
- Judge rates against specification, not just price.
- Make provisional sums realistic and visible.
- Price exclusions to compare quotations fairly.
Get a transparent BOQ
FIXORA Decor provides itemized BOQs with named specifications, realistic allowances and a clear exclusions list for every project in Dubai. Request a detailed quotation or send us your drawings on WhatsApp at +971501962136 and we will walk you through each line.
The information in this article is general guidance, not advice for your specific project. See our Terms.