How to inspect a finished fit-out or renovation in Dubai: a room-by-room snagging checklist, handover documents to collect and how the defects liability period works. Snagging is the inspection of finished work to find defects before you accept the project and make the final payment.
Last updated:
Snagging is the inspection of finished work to find defects before you accept the project and make the final payment. On a Dubai fit-out or renovation, a proper snagging inspection covers finishes, joinery, doors, wet areas, electrical, AC and plumbing, followed by a written list that the contractor must close within an agreed time. Handover should then include as-built drawings, test certificates, warranties and authority completion documents. After handover, the defects liability period, commonly 12 months, protects you against problems that appear later.
When and how to snag
Snag when the contractor declares the work complete and the site is clean. Dust hides scratches and paint defects, so an inspection on a dirty site is wasted. Inspect in daylight and again with all lights on, because raking light from windows and downlights reveals uneven walls and ceiling joints.
Bring a few simple tools: a torch, a spirit level, a socket tester, a roll of low-tack masking tape for marking defects, a measuring tape and a phone for photos. Number each room and record each item with its location, a description and a photo. Agree with the contractor that the list will be a shared document so that everyone is working from the same version.
On larger projects, two rounds work better than one. A pre-handover walk-through with the contractor's supervisor catches most visible issues, and a final inspection a few days later confirms they have been closed and picks up anything missed. Run every tap, shower and AC unit for a while during the inspection; many leaks and drainage problems only appear after water has been flowing for several minutes.
Room-by-room snagging checklist
Walls, ceilings and paint
- Even color and sheen, no patchiness, roller marks, drips or brush marks.
- No visible cracks at plasterboard joints or around door frames.
- Clean straight lines where walls meet ceilings and where colors change.
- Ceiling access panels aligned and closing flush.
Floors
- Tiles level with no lippage between adjacent tiles, consistent grout lines and no hollow-sounding tiles when tapped.
- No chipped tiles, scratched timber or vinyl, and skirting fixed tightly with clean joints.
- Thresholds and transitions between materials secure and level.
Doors, windows and joinery
- Doors open and close freely without binding, with even gaps around the leaf.
- Locks, handles, hinges and door closers working smoothly; keys provided for every lock.
- Wardrobe and kitchen doors aligned, drawers running smoothly, soft-close functions working.
- Edge-banding intact, no exposed board edges, shelves level.
Kitchens and bathrooms
- Taps run hot and cold correctly with adequate pressure, no drips.
- Drains empty quickly; showers have no standing water.
- Silicone continuous and neat around basins, baths, worktops and shower screens.
- WCs flush fully and refill without running on; concealed cistern access works.
- Extraction fans and cooker hoods working and ducted as designed.
- Under-sink areas dry when taps have been running for several minutes.
Electrical and lighting
- Every switch, socket, dimmer and light fitting works, and labels in the distribution board match the circuits.
- Sockets and switch plates straight and fixed flush to the wall.
- Residual current devices trip when tested.
- Data, television and doorbell points working.
Air conditioning
- Each room reaches the set temperature within a reasonable time.
- No condensation dripping from grilles or diffusers, no water staining on ceilings.
- Thermostats control the correct zones; noise levels acceptable.
Villa exteriors and outdoor areas
- External paint even, with no hairline cracks at render joints or around windows.
- Paving and decking level, with falls directing water away from the villa.
- Pergolas, shade structures and gates fixed securely, with no sharp edges or exposed fixings.
- Outdoor lights and sockets weatherproof, typically rated IP65 or higher, and on a protected circuit.
- Irrigation and pool equipment tested and labeled.
Extra checks for offices and shops
- Emergency lighting and exit signs illuminated and tested.
- Fire alarm devices and sprinkler heads uncovered, undamaged and at approved positions.
- Glass partitions marked with manifestation at eye level, and door closers adjusted.
- Data points labeled and tested, with test results provided.
- Accessible routes, toilets and door widths in line with the approved drawings.
How to write a snag list that gets results
A snag list is only useful if the contractor can act on it without guessing. Write each item as location, defect and expected outcome: for example, 'Bedroom 2, wardrobe left door, hinge loose and door drops 3 mm, adjust or replace hinge'. Attach a photo and number the items so progress can be tracked. Avoid vague notes such as 'paint not good'. Group items by trade, because the painter, joiner and electrician will usually visit separately. Agree a date for each group, then re-inspect and sign off items as they are closed. Keep the final signed list with your handover documents, since it forms part of the record if a defect reappears during the defects period.
Be fair as well as thorough. Natural materials vary in tone, plasterboard ceilings may show very faint joint lines under strong side light, and timber can move slightly with humidity. Focus the list on items that fall short of the agreed specification or normal workmanship standards.
Handover documents to collect
The table below lists documents you should receive. Not all apply to every project, but missing items are difficult to obtain later.
| Document | Why it matters | Typical for |
|---|---|---|
| As-built drawings | Show where pipes, cables and ducts actually run | All renovations with MEP changes |
| Test certificates | Electrical, pressure, flood and AC balancing tests | All projects with services work |
| Warranties and guarantees | Equipment, waterproofing, joinery and workmanship cover | All projects |
| Operation and maintenance manuals | How to use and service equipment | AC, water heaters, appliances, smart systems |
| Authority completion documents | Proof work was approved and inspected | Structural, extension and commercial fit-outs |
| Building or developer clearance | Release of security deposit | Towers and gated communities |
Defects liability period and retention
Most fit-out contracts in Dubai include a defects liability period, commonly 12 months from handover. During this time, the contractor must return to fix defects caused by materials or workmanship, such as a tile that cracks, a door that drops or a leak that appears. It does not cover damage from misuse or normal wear.
Many contracts also include retention: a percentage of the contract value, commonly 5–10%, withheld until the end of the defects period, or split between practical completion and the end of the period. On smaller residential projects, retention is sometimes replaced by a written workmanship warranty. Whichever applies, put defects in writing as soon as you notice them and keep a log with dates and photos. Under Federal Law No. 15 of 2020 on consumer protection, consumers also have statutory rights regarding defective goods and services, which sit alongside the contract.
At FIXORA Decor we schedule a check visit before the defects period ends, so that anything noted during the year is closed before retention is released.
Common mistakes
- Moving furniture in before snagging, which hides floor and wall defects and makes it unclear who caused damage.
- Accepting verbal promises to fix items instead of a written list with target dates.
- Making the final payment before major snags are closed.
- Not testing every outlet and tap because they look fine.
- Losing warranty documents, which are needed for any equipment claim.
If you are still choosing a contractor, our guide to questions to ask a fit-out contractor covers warranties and defects terms to agree in advance.
Next step
Whether you are planning a new project or need help closing out defects on a recent one, FIXORA Decor can assist. Request a free quotation, or ask about our home maintenance service for repairs and ongoing upkeep after handover.
The information in this article is general guidance, not advice for your specific project. See our Terms.